List the assessment methods to be used and the context and resources required for assessment. Copy and paste the relevant sections from the evidence guide below and then re-write these in plain English.
Element | Performance criteria |
Elements describe the essential outcomes. | Performance criteria describe the performance needed to demonstrate achievement of the element. |
1. Apply commonly used symbols and abbreviations | 1.1 Identify, understand and apply commonly used symbols and abbreviations on plans 1.2 Identify, understand and apply common irrigation terms used on plans 1.3 Identify key features of irrigation plans, elevations and sections 1.4 Identify scale, elevations and sections from drawings |
2. Locate and identify key features on a site plan | 2.1 Identify irrigation site from location drawings 2.2 Identify true north and system orientation from details provided on site plan 2.3 Identify key features of site plan |
3. Mark out and peg the site from a plan | 3.1 Mark boundaries of the site 3.2 Identify existing irrigation infrastructure on the site 3.3 Identify electricity and communications infrastructure on the site plan, mark out and implement safety procedures 3.4 Peg out pipelines and earthworks identified on the plan |
4. Identify required components for installation | 4.1 Annotate required pipeline components from plans and drawings 4.2 Annotate water supply, distribution and delivery components from plans and drawings 4.3 Make provision for receival and storage of materials on site 4.4 Confirm installation requirements and details of plans and drawings with supervisor |
The candidate must be assessed on their ability to integrate and apply the performance requirements of this unit in a workplace setting. Performance must be demonstrated consistently over time and in a suitable range of contexts.
The candidate must provide evidence that they can:
interpret scale and specifications from plans and drawings
interpret symbols and abbreviations used on plans
mark out boundaries and infrastructure position from a plan
recognise and mark out features on a site from a plan
translate documented requirements into on-site activities and site and structural features from two-dimensional to three-dimensional formats
use basic industry calculations
The candidate must demonstrate knowledge of:
principles and practices of plan and drawing interpretation
commonly used scales, symbols and abbreviations
drawings and specifications relevant to the irrigation industry
measurements, calculations and quantities
tools, equipment and materials required from the drawings and specifications
Assessors must satisfy current standards for RTOs.