List the assessment methods to be used and the context and resources required for assessment. Copy and paste the relevant sections from the evidence guide below and then re-write these in plain English.
The candidate must demonstrate the ability to complete the tasks outlined in the elements, performance criteria and foundation skills of this unit, including evidence of the ability to:
support project managers and other team members to apply project time management techniques during at least two different projects.
In the course of the above, the candidate must:
create a project schedule showing tasks, deliverable milestones, sequence, dependencies and time estimates
apply time-management techniques in a project
use relevant tools and techniques to maintain, monitor and update a project schedule.
The candidate must be able to demonstrate knowledge to complete the tasks outlined in the elements, performance criteria and foundation skills of this unit, including knowledge of:
contents of work breakdown structure detail to enable effective project planning and control
implications of time management for project resources, costs and risks
methods for estimating task duration and resource requirements
tools and techniques for managing project time and their particular applications
methods to evaluate the effectiveness of time management
techniques used to measure, record and report progress of activities.
Skills in this unit must be demonstrated in a workplace or simulated environment where the conditions are typical of those in a working environment in this industry.
This includes access to:
workplace documentation relevant to project management
planning tools.
Assessors of this unit must satisfy the requirements for assessors in applicable vocational education and training legislation, frameworks and/or standards.