Assessor Resource

ICTOPN405
Install and test a dense wavelength division multiplexing system

Assessment tool

Version 1.0
Issue Date: May 2024


This unit describes the skills and knowledge required to install dense wavelength division multiplexing (DWDM) equipment in optical networks.

It applies to technicians who interpret installation manuals and use technical skills to prepare for and conduct system tests and commissioning.

No licensing, legislative or certification requirements apply to this unit at the time of publication.

You may want to include more information here about the target group and the purpose of the assessments (eg formative, summative, recognition)

Submission Requirements

List each assessment task's title, type (eg project, observation/demonstration, essay, assingnment, checklist) and due date here

Assessment task 1: [title]      Due date:

(add new lines for each of the assessment tasks)


Assessment Tasks

Copy and paste from the following data to produce each assessment task. Write these in plain English and spell out how, when and where the task is to be carried out, under what conditions, and what resources are needed. Include guidelines about how well the candidate has to perform a task for it to be judged satisfactory.
Copy and paste from the following performance criteria to create an observation checklist for each task. When you have finished writing your assessment tool every one of these must have been addressed, preferably several times in a variety of contexts. To ensure this occurs download the assessment matrix for the unit; enter each assessment task as a column header and place check marks against each performance criteria that task addresses.

Observation Checklist

Tasks to be observed according to workplace/college/TAFE policy and procedures, relevant legislation and Codes of Practice Yes No Comments/feedback
Determine number of racks and DWDM units at each site according to installation documents 
Determine DWDM unit and equipment positions within individual racks 
Assemble equipment racks according to safe industry practice and manufacturer instructions 
Select tools and equipment for DWDM unit installation 
Prepare patch panels with connectors according to installation plan 
Install DWDM unit in designated rack position to maintain planned link budget margin 
Install patch panels and ancillary equipment and connections into equipment rack in preparation for commissioning procedures 
Insert circuit cards into specified slot locations in readiness for commissioning procedures without seating cards into backplane or locking into position 
Connect optical fibre cables between circuit cards, optical multiplexers, adjoining DWDM units and patch panels, according to manufacturer specifications 
Seat cards into backplane and lock into position 
Measure main and redundant power supplies to verify correct polarity of ground and power connections 
Rectify any identified power wiring fault as required 
Confirm cooling fans, panel lights, indicator lights and alarms behave according to manufacturer prescribed specifications when power is applied 
Complete installation report and reinstate site 

Forms

Assessment Cover Sheet

ICTOPN405 - Install and test a dense wavelength division multiplexing system
Assessment task 1: [title]

Student name:

Student ID:

I declare that the assessment tasks submitted for this unit are my own work.

Student signature:

Result: Competent Not yet competent

Feedback to student

 

 

 

 

 

 

 

 

Assessor name:

Signature:

Date:


Assessment Record Sheet

ICTOPN405 - Install and test a dense wavelength division multiplexing system

Student name:

Student ID:

Assessment task 1: [title] Result: Competent Not yet competent

(add lines for each task)

Feedback to student:

 

 

 

 

 

 

 

 

Overall assessment result: Competent Not yet competent

Assessor name:

Signature:

Date:

Student signature:

Date: