Assessor Resource

UEPOPS343
Operate hydroelectric generating plant and auxiliary equipment

Assessment tool

Version 1.0
Issue Date: May 2024


This unit involves the skills and knowledge required to operate a hydroelectric power generating facility. It includes the operational and maintenance activities associated with hydroelectric operating plant and auxiliary equipment.

Auxiliary plant systems and related controls are used to support the operation of hydro generating facilities. Auxiliary plant systems typically include ancillary equipment such as pumps, valves, seals and screens, motors, waterwheels and generators.

Competency in this unit requires the ability to plan and prepare work, operate, test, analyse and report on hydroelectric generating plant and auxiliary equipment. Individuals will, in general, work under supervision, in a power generation facility as an operator.

Power generation plant operators are typically trained and authorised to isolate, prepare plant and issue permits to work.

No licensing, legislative or certification requirements apply to this unit at the time of publication.

Note: Workplace practice

The application of the skills and knowledge described in this unit may require a licence or training permit to practice in the workplace where work is carried out on gas and electrical installations. Additional conditions may apply under state and territory legislative and regulatory licensing requirements.

You may want to include more information here about the target group and the purpose of the assessments (eg formative, summative, recognition)

Submission Requirements

List each assessment task's title, type (eg project, observation/demonstration, essay, assingnment, checklist) and due date here

Assessment task 1: [title]      Due date:

(add new lines for each of the assessment tasks)


Assessment Tasks

Copy and paste from the following data to produce each assessment task. Write these in plain English and spell out how, when and where the task is to be carried out, under what conditions, and what resources are needed. Include guidelines about how well the candidate has to perform a task for it to be judged satisfactory.

Range is restricted to essential operating conditions and any other variables essential to the work environment.

Non-essential conditions may be found in the Companion Volume Implementation Guide.

Copy and paste from the following performance criteria to create an observation checklist for each task. When you have finished writing your assessment tool every one of these must have been addressed, preferably several times in a variety of contexts. To ensure this occurs download the assessment matrix for the unit; enter each assessment task as a column header and place check marks against each performance criteria that task addresses.

Observation Checklist

Tasks to be observed according to workplace/college/TAFE policy and procedures, relevant legislation and Codes of Practice Yes No Comments/feedback
Work, Health and Safety(WHS)/Occupational Health and Safety (OHS) regulations, legislative requirements, industry standards, codes of practice, manufacturers’ specifications, environmental obligations and workplace procedures are applied and monitored 
Work, hydroelectric generating plant and type of start requirements are identified from appropriate personnel and documentation, in accordance with workplace procedures 
Turbine running-up and loading schedules are ascertained from relevant documentation, in accordance with workplace procedures and site requirements 
Hydroelectric generating plant and auxiliary equipment inspections, preoperational tests and field preparation for service are carried out, in accordance with manufacturers' recommendations and workplace procedures 
Hydroelectric generating plant and auxiliary equipment operational prerequisites are established, in accordance with manufacturers' recommendations and workplace procedures 
Sequence for recommissioning hydroelectric generating plant and auxiliary equipment is determined, in accordance with workplace procedures and site requirements 
Work is sequenced and prioritised, in accordance with workplace procedures and site requirements 
 
 
 
 
 
 
Hydroelectric generating plant is operated, in accordance with workplace procedures and manufacturers' recommendations 
 
 
 
 
 
Tests on hydroelectric generating plant and equipment are performed, in accordance with workplace procedures 
 
 
Causes of abnormal operating conditions are identified by analysing technical and operational information, in accordance with workplace procedures 
 
 
Equipment problems, movements and status are reported, in accordance with workplace procedures 
 

Forms

Assessment Cover Sheet

UEPOPS343 - Operate hydroelectric generating plant and auxiliary equipment
Assessment task 1: [title]

Student name:

Student ID:

I declare that the assessment tasks submitted for this unit are my own work.

Student signature:

Result: Competent Not yet competent

Feedback to student

 

 

 

 

 

 

 

 

Assessor name:

Signature:

Date:


Assessment Record Sheet

UEPOPS343 - Operate hydroelectric generating plant and auxiliary equipment

Student name:

Student ID:

Assessment task 1: [title] Result: Competent Not yet competent

(add lines for each task)

Feedback to student:

 

 

 

 

 

 

 

 

Overall assessment result: Competent Not yet competent

Assessor name:

Signature:

Date:

Student signature: