Elements and Performance Criteria
- Plan and prepare.
- Work instructions and operational details are obtained using relevant information, confirmed and applied for planning and preparation purposes.
- Safety (OHS) requirements are followed in accordance with safety plans and policies.
- Signage and barricade requirements are identified and implemented.
- Tools and equipment selected to carry out tasks are consistent with the requirements of the job, checked for serviceability and any faults are rectified or reported prior to commencement.
- Material quantity requirements are calculated in accordance with plans and specifications and quality requirements.
- Materials appropriate to the work application are identified, obtained, prepared, safely handled and located ready for use.
- Environmental requirements are identified for the project in accordance with environmental plans and regulatory obligations and applied.
- Identify levels of finish.
- Establish level of finish requirements.
- Workplace documents, specifications, contract and/or supervisors are used to establish customer levels of finish requirements.
- Recommended work practices to produce required level of finish required by the customer are identified.
- Required modifications to materials or work processes to meet required level of finish are identified.
- Required modifications to materials or work methods are communicated to appropriate personnel.
- Inspect completed work for level of finish.
- Distinguishing features of levels of finish are identified in the completed work.
- Effects of framing tolerances, windows, light fittings and location of joins on finish of plasterboard are explained.
- Identified features are compared to level of finish descriptions.
- Build-up on joins is inspected for influence on level of finish.
- Level of finish classification is allocated to inspected work.
- Provide advice for surface finishing.