Elements and Performance Criteria
- Plan and prepare.
- Work instructions, including plans, specifications, quality requirements and operational details are obtained from relevant information, confirmed and applied to the scope of work performed.
- Reinforced concrete construction schedule is identified from project schedule.
- Elements of structure are identified from project construction schedule and job drawings.
- Safety (OHS) requirements are followed in accordance with safety plans and policies.
- Environmental requirements are identified for the project in accordance with environmental plans and statutory and legislative authority obligations and applied.
- Read and interpret schedule.
- Structural element to be constructed is confirmed from site and structural detail drawings.
- Reinforcement schedule is read to identify the appropriate reinforcement type for the structural element.
- Number of reinforcement pieces/sheets is identified from structural detail drawings.
- Reinforcement schedule is read to identify coding and number related to labels.
- Discrepancies in coding and numbering are identified and situation is reported to schedule contact for clarification.
- Check contents of bundles.
- Content of reinforcement material bundles is checked for conformity to schedule and proposed structural element.
- Discrepancies between the schedule and actual material quantities are investigated and resolved or reported.
- Discrepancies between the schedule and actual material shape, size or length are investigated and resolved or reported.
- Cranked or bent items of reinforcement are identified, segregated and reported.
- Schedule is marked where content conforms to schedule and structural element's requirements.
- Locate reinforcement for element construction.
- Communicate schedule information.
- Job sequencing schedule detail is communicated to steel fixers and team members to ensure efficient work practices.
- Changes to job sequencing schedule are recorded as per site requirements.
- Work completion procedures are identified and relevant personnel notified when finished, as per site requirements.