Elements and Performance Criteria
- Determine job requirements
- Follow standard operating procedures (SOPs)
- Comply with work health and safety (WHS) requirements at all times, including appropriate risk control measures
- Use appropriate personal protective equipment (PPE) in accordance with SOPs
- Consult and obtain approval from authorised personnel the need to commission or decommission electrical equipment or installation
- Analyse and confirm commissioning, switching and work schedules, including drawings, plans and regulatory requirements
- Prepare to commission or decommission electrical equipment or installation
- Inspect or confirm suitability and safety of electrical equipment or installation site for required commissioning or decommissioning
- Identify and obtain WHS policies and procedures related to the requirements for commissioning or decommissioning electrical equipment or installation
- Obtain necessary tools, equipment and testing devices needed for commission or decommission electrical equipment or installation
- Brief others participating in or affected by the work on commissioning or decommissioning of electrical equipment or installation
- Prepare the site according to the work schedule to minimise risk, disruption and damage to property, operations and individuals
- Commission or decommission electrical equipment or installation
- Commission electrical equipment or installation using a systems approach, including the use of appropriate test equipment, in accordance with the approved commissioning schedule
- Verify that the performance of the installed equipment/installation through a series of tests is consistent with the customer requirements/specified design intent
- Capture and record performance data of the whole installation as the baseline for future operation and maintenance
- Decommission electrical equipment or installation using an approved decommissioning schedule, including the use of appropriate test equipment, according to requirements and established procedures
- Shut down and isolate electrical equipment or installation sequentially in preparation for repair or maintenance work using safe working practices
- Deal safely with unexpected situations during the isolation process, including, where required, the approval of an authorised person
- Complete commission or decommission electrical equipment or installation