Elements and Performance Criteria
- Prepare to erect scaffold/equipment
- Erect scaffold/equipment
- Erection site is prepared to meet job requirements.
- Necessary signage and barriers and third party protection measures are placed in appropriate position.
- Appropriate scaffolding/equipment components are selected and inspected and damaged components are labelled and rejected.
- Rejected components are repaired or sent for repair.
- Scaffolding/equipment is erected to plan and in accordance with safe work practices, Australian standards, State and Territory legislative requirements and equipment manufacturers' requirements.
- The completed scaffolding/equipment is checked for safety and operational requirements.
- Site is left clear of all surplus components, equipment, tools and debris.
- Inspect, repair and alter scaffold/equipment
- Dismantle scaffold/equipment
- Work is undertaken safely and to prescribed procedure.
- Scaffolding/equipment is inspected for damage, corrosion or wear and is noted for consideration in planning for dismantling.
- Scaffolding/equipment is dismantled in accordance with site procedures, State and Territory legislative requirements and critical structural and safety requirements.
- Site is cleaned and cleared of all tools, excess material and debris and left in a safe state.