Elements and Performance Criteria
- Plan for maintenance of poles and associated hardware
- Works order is received/accessed, analysed and confirmed, if necessary by site inspection
- Resources required for the job are identified and scheduled
- Replacement or additional poles, associated hardware and plant/equipment are transported to the worksite
- Liaison and communication issues are resolved
- Prepare the worksite
- Personnel participating in task, including plant operators and contractors, are fully briefed
- Road signs, barriers and warning devices are positioned, and worksite protection is provided
- Safeworking practices are observed on or about the running line/track
- Replacement or additional poles and associated hardware are placed in planned assembly and/or pre-lift location
- Excavation/foundation is inspected and confirmed as being in accordance with the works order or specification
- Conduct maintenance of poles and associated hardware
- Complete the work