Elements and Performance Criteria
- Prepare for welding
- Weld requirements are identified from specifications and/or technical drawings
- Rail surface is correctly prepared using tools and techniques appropriate to the material and process
- Materials are assembled/aligned to specifications as required
- Track is measured prior to commencement of welding
- Welding machine settings and consumables are identified from job requirements, welding procedures, specifications and/or technical drawings
- Hazards are identified, risks are assessed and control measures are implemented
- Assemble and set up equipment
- Welding equipment is assembled and set up safely and correctly in accordance with operating procedures
- Defective equipment is tagged and replaced in accordance with organisational and manufacturer specifications
- Weld rail using submerged arc process
- Pad, butt and fillet welds are deposited correctly in flat and fillet welds in horizontal position in accordance with specifications
- Joints are cleaned to specifications using techniques and tools appropriate to the defect, material and process
- Inspect welds and correct faults
- Weld joints are visually inspected against specifications
- Track is measured to ensure welded track is within accepted tolerances
- Weld defects are identified and remedial action is taken, where required
- Defects are removed with minimum loss of sound metal using techniques and tools appropriate to the defect, material and process
- Maintain weld records
- Weld records are filled in legibly and proofread
- Weld records are processed in accordance with organisational procedures