Elements and Performance Criteria
- Prepare to develop and validate basic integrated systems.
- OHS processes and procedures for a given work area are identified, obtained and understood.
- The extent and nature of the integrated system is determined from design brief.
- Safety and other regulatory requirements to which the electrical installation shall comply area are identified, obtained and understood.
- Work supervisor or customers are consulted to determine which functions of the system are to be use and the parameter of each and written confirmation sought.
- Software, tools, equipment and testing devices needed to carry out the work are obtained and checked for correct operation and safety.
- Develop and validate basic integrated systems.
- Established OHS risk control measures and procedures for carrying out the work are followed.
- Knowledge of integrated systems, electrical and other services, installation performance standards, compliance methods and service equipment is applied to developing the integrated system.
- System installation requirements, equipment and instructions for the integrated system are incorporated in the development.
- Safety, functional and budgetary considerations are incorporated in the installation design.
- Equipment required for the integrated system is selected and obtained in accordance with the developed plan and established requirements.
- The required status of each function of system devices is entered and their parameters set in accordance manufactures programming instructions and customer's requirements.
- Location of each device in the installation of the integrated system is documented to ensure correct operation of system functions.
- Solutions to unplanned situation are provided consistent with organisation's policy.
- Validate integrated system and report.
- System device operations are tested in strict accordance OHS requirements and procedures.
- Operating anomalies are identified and corrected in accordance with established routines.
- OHS work completion risk control measures and procedures are followed.
- Work site is cleaned and made safe in accordance with established procedures.
- Work completion is documented and appropriate person(s) notified in accordance with established routines.