Elements and Performance Criteria
- Prepare to conduct periodic maintenance on wind generators
- OHS procedures for a RAPS plant are identified, obtained and understood through established routines and procedures
- Established OHS risk control measures and procedures in preparation for the work are followed.
- Safety hazards which have not previously been identified are reported and advice on risk control measures is sought from the work supervisor.
- The nature and location of RAPS system is identified from documentation or from work supervisor to establish the scope of work to be undertaken.
- Advice is sought from the work supervisor to ensure the work is coordinated effectively with fellow workers and the local community.
- Sources of materials that may be required for the work are identified and accessed in accordance with established routines and procedures.
- Tools, equipment and testing devices needed to carry out the work are obtained and checked for correct operation and safety
- Maintain RAPS systems wind generators
- Established OHS risk control measures and procedures for carrying out the work are followed.
- The need to test or measure live is determined in strict accordance with OHS requirements and when necessary conducted within established safety procedures
- Circuits/machines/plant are checked as being isolated where necessary in strict accordance OHS requirements and procedures
- Prescribed maintenance procedures are used to test and check RAPS system wind generators
- Wind generator maintenance, including performance measurements and repairs, are carried out safely and to prescribed routines and procedures.
- Known types of wind generator functional faults are identified using routine fault finding procedures.
- Procedures are followed for referring non-routine events to immediate supervisor for directions.
- Maintenance and repair work is carried out efficiently without waste of materials and energy and without damage to apparatus, circuits, the surrounding environment or services
- Routine quality checks are carried out in accordance with work instructions.
- Complete maintenance work of wind generators and report
- OHS work completion risk control measures and procedures are followed.
- Work site is cleaned and made safe in accordance with routine procedures.
- Procedures for referring local maintenance issues to the community are followed.
- Wind generator performance measurements are reported to the work supervisor through the established maintenance reporting procedures.