Google Links

Follow the links below to find material targeted to the unit's elements, performance criteria, required skills and knowledge

Elements and Performance Criteria

  1. Prepare and plan for pigging gas distribution pipelines
  2. Job requirements and workplace procedures for the work are obtained and discussed with relevant person/s to confirm the work schedule
  3. WHS/OHS, environmental and sustainable energy policies and procedures are obtained and applied
  4. Hazards are identified, WHS/OHS risks are assessed and control measures prioritised, implemented and monitored in accordance with workplace procedures
  5. Responsibilities under the relevant work permit/notification are obtained and confirmed with relevant person/s to access, isolate/de-isolate systems and perform the work in accordance with regulatory requirements and workplace procedures
  6. Personnel, equipment, tools and personal protective equipment (PPE) required for the work are identified, scheduled, obtained and checked for correct operation and safety in accordance with workplace procedures
  7. Materials, plans, diagrams, drawings and resources required for work are confirmed, scheduled and obtained in accordance with workplace procedures
  8. Responsibilities for first aid and other emergency incidents at the work site are checked and confirmed with relevant person/s in accordance with workplace procedures
  9. Communication with authorised person/s, authorities, clients and land-owners is conducted and work coordinated in accordance with work schedule and workplace procedures
  10. Site preparation, safety plan and work schedule are confirmed in accordance with workplace procedures
  11. Site, PIG, PIG trap and pipeline are prepared to minimise risk and damage to property, commerce and individuals in accordance with workplace procedures
  12. Person/s participating in the work, including plant operators and contractors, are briefed and responsibilities confirmed in accordance with workplace procedures
  13. Road signs, barriers and warning devices are positioned in accordance with job requirements, workplace procedures and traffic management plan
  14. Launch and recover gasdistribution pipeline PIGs
  15. Materials, tools, equipment and measuring devices required for the work are selected and used correctly and safely in accordance with manufacturer instructions
  16. Hazardous activities and use of power tools, techniques and practices are conducted safely in accordance with job instructions, regulatory requirements and workplace procedures
  17. Launch and recovery of gas distribution pipeline PIG is carried out in accordance with work schedule and workplace procedures
  18. Work is carried out to industry standards without waste of materials or damage to apparatus, circuits, and the surrounding environment or services using sustainable energy principles
  19. Data/results from distribution pipeline pigging operations is gathered/retrieved and analysed to determine internal pipeline conditions in accordance with workplace procedures
  20. Testing and inspecting of pipeline and pigging equipment is conducted in accordance with job requirements and workplace procedures
  21. Hazards are identified and WHS/OHS risks are assessed and incidents reported to authorised person/s for directions in accordance with workplace procedures
  22. Unplanned events and non-routine problems are referred to authorised person/s for direction in accordance with workplace procedures
  23. Quality and safety checks of the work are undertaken in accordance with industry standards and workplace procedures
  24. Re-establish distribution pipeline to operational condition, andcomplete work and relevant documentation
  25. Retrieved PIG is inspected to determine the wear sustained to the PIG, material is checked against works schedule for conformance and anomalies reported in accordance with workplace procedures
  26. Waste materials are safely disposed of and work site is rehabilitated, cleaned up and made safe in accordance with workplace procedures
  27. Tools, equipment and any surplus resources and materials are cleaned, checked and securely stored in accordance with workplace procedures
  28. Appropriate person/s are notified of work completion in accordance with workplace procedures
  29. Relevant work permit/s are signed off and pipeline returned to service in accordance with regulatory requirements and workplace procedures
  30. Data is recorded and work completion documentation is completed and provided to the appropriate person/s in accordance with workplace procedures

Range Statement

Range is restricted to essential operating conditions and any other variables essential to the work environment.

Non-essential conditions may be found in the UEG Gas Industry Training Package Companion Volume Implementation Guide.

launch and recovery of PIGs in new or decommissioned gas distribution main pipelines must include:

prepare PIG trap for launch

connections to compressors

prepare trap for receiving

determine volume of water /compressor requirements from chart/table needed

install disc PIG

carry out pigging operation

install foam PIG

carry out pigging operation

recover PIG

pressure test pipeline