Elements and Performance Criteria
- Plan and prepare for the work
- Work requirements are identified from request/work orders or equivalent and clarified/confirmed with appropriate parties or by site inspection
- Occupational Health and Safety standards, statutory requirements, relevant Australian standards, codes of practice, manufacturers' specifications, environmental requirements and enterprise procedures are identified, applied and monitored throughout the work procedure
- Resources required to satisfy the work plan are identified, obtained and inspected for compliance with the job specifications
- Relevant plans, drawings and texts are selected and interpreted in accordance with the work plan
- Correct size, type and quantity of materials/components are determined, obtained and inspected for compliance with the job specifications
- Work is planned in detail including sequencing and prioritising and considerations made, where appropriate, for the maintenance of plant security and capacity in accordance with system/site requirements
- Coordination requirements, including requests for isolations where appropriate, are resolved with others involved, affected or required by the work
- Potential hazards are identified and prevention and/or control measures are selected in accordance with the work plan and site procedures
- Work area is prepared in accordance with work requirements and site procedures
- Where appropriate, the teams and individuals roles and responsibilities within the team are identified and, where required, assist in the provision of the on-the-job training
- Carry out maintenance
- Required isolations are confirmed where appropriate in accordance with site requirements
- Equipment is maintained using appropriate plans, drawings and texts in accordance with the work plan
- Equipment is maintained in conjunction with others involved in, or affected by, the work in accordance with the work plan
- Calibration and/or adjustments required are carried out to ensure equipment operates within requirements in accordance with the work plan
- Maintenance and calibration/adjustments carried out mindful of effects on, or unnecessary loss of, other equipment
- Final job inspection is carried out and permits relinquished in accordance with the work plan.
- Complete the work
- Work is completed and appropriate personnel notified in accordance with site/enterprise requirements
- Work area is cleared of waste, cleaned, restored and secured in accordance with site/enterprise procedures
- Plant, tools and equipment are maintained and stored in accordance with site/enterprise procedures
- Work completion details are finalised in accordance with site/enterprise procedures