Follow the links below to find material targeted to the unit's elements, performance criteria, required skills and knowledge
Elements and Performance Criteria
- Test system
- Isolations are confirmed, where appropriate, in accordance with workplace procedures
- Wind turbine control system is visually inspected to ensure absence of any damage, defects or deterioration, in accordance with workplace procedures and commissioning plan
- Wind turbine control system is tested using appropriate plans, drawings and manuals, in accordance with workplace procedures and commissioning plan
- Wind turbine control system is tested, in conjunction with other related systems and equipment, in accordance with workplace procedures and commissioning plan
- Wind turbine control system test results are interpreted and documented, in accordance with workplace procedures, to confirm compliance with commissioning plan
- Commission system
- Isolations are confirmed, where appropriate, in accordance with workplace procedures
- Wind turbine control system plant and equipment is set up, in accordance with workplace procedures, to meet operational requirements and manufacturers' specifications
- Wind turbine control system is set up, in accordance with workplace procedures, to meet operational requirements and manufacturers' specifications
- Wind turbine control system plans, drawings and manuals are used, in accordance with workplace procedures and commissioning plan
- Wind turbine control system equipment is commissioned, in accordance with workplace procedures and commissioning plan
- Faulty wind turbine control system equipment is repaired, or reported, in accordance with workplace procedures
- Final inspection is carried out, in accordance with workplace procedures
- Complete work
- Plan and prepare for work
- Work, Health and Safety (WHS)/Occupational Health and Safety (OHS) regulations, legislative requirements, industry standards, codes of practice, manufacturers’ specifications, environmental obligations and workplace procedures are reviewed in preparation for work
- Resources are obtained and inspected for compliance with job specification
- Relevant plans, drawings and manuals are selected and used, in accordance with workplace procedures
- Correct materials and components for work are obtained and inspected for compliance with job specification
- Plan for commissioning of wind turbine control system is developed, in accordance with workplace procedures, including sequencing and prioritising
- Potential hazards are identified and risk control measures are implemented, in accordance with workplace procedures
- Work area is prepared in accordance with workplace procedures
- Test systems equipment
- Wind turbine control system equipment is visually inspected to ensure absence of any damage, defects or deterioration, in accordance with workplace procedures and commissioning plan
- Wind turbine control system equipment is tested, in conjunction with other related systems and equipment, to ensure correct operation, in accordance with workplace procedures and commissioning plan
- Wind turbine control system wiring system is checked and tested, in conjunction with other related systems and equipment, in accordance with workplace procedures and commissioning plan
- Wind turbine control system is visually inspected to ensure absence of any damage, defects or deterioration, in accordance with workplace procedures and commissioning plan
- Wind turbine control system is tested using appropriate plans, drawings and manuals, in accordance with workplace procedures and commissioning plan
- Wind turbine control system is tested, in conjunction with other related systems and equipment, in accordance with workplace procedures and commissioning plan
- Wind turbine control system test results are interpreted and documented, in accordance with workplace procedures, to confirm compliance with commissioning plan
- Wind turbine control system plant and equipment is set up, in accordance with workplace procedures, to meet operational requirements and manufacturers' specifications
- Wind turbine control system is set up, in accordance with workplace procedures, to meet operational requirements and manufacturers' specifications
- Wind turbine control system plans, drawings and manuals are used, in accordance with workplace procedures and commissioning plan
- Wind turbine control system equipment is commissioned, in accordance with workplace procedures and commissioning plan
- Faulty wind turbine control system equipment is repaired, or reported, in accordance with workplace procedures
- Final inspection is carried out, in accordance with workplace procedures
- Work area is cleared of waste, cleaned, restored and secured in accordance with workplace procedures
- Tools and equipment are maintained and stored, in accordance with workplace procedures
- Work completion details are finalised in accordance with workplace procedures
Range Statement