- Plan and prepare work
- Safety issues related to operating and monitoring hydro plant auxiliary system are identified, in accordance with workplace procedures and Work, Health and Safety (WHS)/Occupational Health and Safety (OHS) regulations and legislative requirements
- Work tasks, hydro plant auxiliary system requirements are identified, in accordance with workplace procedures, from appropriate personnel and documentation
- Hydro plant auxiliary system running-up and loading schedule are ascertained, in accordance with workplace procedures, and from relevant documentation
- Inspection, preoperational tests and field preparation for hydro plant auxiliary system service are carried out, in accordance with workplace procedures and manufacturers' recommendations
- Hydro plant auxiliary system operational prerequisites are established, in accordance with workplace procedures and manufacturers' recommendations
- Sequence for recommissioning of hydro plant auxiliary system is determined, in accordance with workplace procedures and site requirements
- Work tasks, hydro plant auxiliary system requirements are identified, in accordance with workplace procedures, from appropriate personnel and documentation
- Hydro plant auxiliary system running-up and loading schedule are ascertained, in accordance with workplace procedures, and from relevant documentation
- Inspection, preoperational tests and field preparation for hydro plant auxiliary system service are carried out, in accordance with workplace procedures and manufacturers' recommendations
- Hydro plant auxiliary system operational prerequisites are established, in accordance with workplace procedures and manufacturers' recommendations
- Sequence for recommissioning of hydro plant auxiliary system is determined, in accordance with workplace procedures and site requirements
- Test hydro plant auxiliary system operation
- Operational tests are performed, in accordance with workplace procedures
- Hydro plant auxiliary system plant is observed, in accordance with workplace procedures, for correct operational response
- Corrective action is taken, in accordance with workplace procedures, when response does not meet with documentation, hydro plant auxiliary system integrity or personnel safety requirements
- Hydro plant auxiliary system is returned to required operational status upon completion of testing, in accordance with workplace procedures
- Analyse hydroplantauxiliary systemfaults
- Corrective actions to rectify faults are determined, in accordance with workplace procedures
- Hydro plant auxiliary system integrity and personnel safety is maintained, in accordance with workplace procedures, and in consultation with appropriate personnel and technical and operational documentation
- Monitor and inspect hydroplantauxiliary system
- Hydro plant auxiliary system is monitored and inspected, in accordance with workplace procedures, for normal operation or to detect deviations
- Appropriate personnel are notified when defects are detected, in accordance with workplace procedures
- Complete documentation
- Documentation is updated, in accordance with workplace procedures
Range Statement