- Plan and prepare work
- Work requirements and generator and/or alternator auxiliary plant are identified from appropriate personnel and documentation, in accordance with workplace procedures
- Generator and/or alternator auxiliary running up and loading schedule is ascertained from relevant documentation, in accordance with workplace procedures and site requirements
- Inspection, preoperational tests and field preparations for generator and/or alternator auxiliary plant service are carried out, in accordance with workplace procedures and manufacturers' recommendations
- Generator and/or alternator auxiliary plant operational prerequisites are established, in accordance with workplace procedures and manufacturers' recommendations
- Sequence for recommissioning of generator and/or alternator auxiliary plant is determined, in accordance with workplace procedures and site requirements
- Operate generator/alternator auxiliaryplant
- Generator and/or alternator auxiliary plant is monitored and observed, in accordance with workplace procedures, to detect deviations from required operating conditions
- Corrective actions are taken to rectify generator and/or alternator auxiliary plant abnormalities, in accordance with workplace procedures and manufacturers' recommendations
- Test generator/alternator auxiliaryplant operation
- Generator and/or alternator auxiliary plant is observed for correct operational response, in accordance with workplace procedures
- Corrective action is taken, in accordance with workplace procedures, when response does not meet with documentation, generator or alternator auxiliary plant integrity or personnel safety requirements
- Generator and/or alternator auxiliary plant is returned to required operational status upon completion of testing, in accordance with workplace procedures
- Analyse generator/alternator auxiliaryplant faults
- Corrective actions to rectify generator and/or alternator auxiliary plant faults are determined, in accordance with workplace procedures
- Generator and/or alternator auxiliary plant integrity and personnel safety is maintained, in accordance with workplace procedures, and in consultation with appropriate personnel and technical and operational documentation
- Monitor and inspect generator/alternator auxiliaryplant
- Generator and/or alternator auxiliary plant is monitored and inspected, in accordance with workplace procedures, for normal operation or to detect deviations
- Corrective action is taken, in accordance with workplace procedures
- Appropriate personnel are notified, in accordance with workplace procedures, when defects are detected
- Complete documentation
- Documentation is updated, in accordance with workplace procedures