  1. Plan and prepare work
  2. Analyse system faults
  3. Work requirements are identified from relevant personnel and documentation, in accordance with workplace procedures
  4. Preoperational checks are carried out on HRSG plant in accordance with manufacturers' recommendations and workplace procedures and site requirements
  5. Operate HRSGplantduring shutdown
  6. Gas turbine exhaust gas flow and power output are adjusted to achieve required steam temperature, pressure and flow conditions, in accordance with workplace procedures
  7. Feedwater flows are adjusted to achieve required steam conditions and demand in accordance with workplace procedures
  8. HRSG plant is maintained in required out of service condition, in accordance with workplace procedures and manufacturers' recommendations
  9. HRSG plant is operated within limits of its' design, in accordance with workplace procedures
  10. HRSG plant is monitored, in accordance with workplace procedures to detect deviations from required operating conditions
  11. Corrective action is taken to rectify HRSG plant abnormalities, in accordance with manufacturers' recommendations and workplace procedures
  12. Test HRSG plant operationduring shut down
  13. Power generation system and HRSG plant are observed for correct operational response, in accordance with workplace procedures
  14. Corrective action is taken, in accordance with workplace procedures, when response does not meet documentation, HRSG plant integrity or personnel safety requirements
  15. HRSG plant is returned to required operational status upon completion of testing, in accordance with workplace procedures
  16. Corrective action is taken, in accordance with workplace procedures
  17. HRSG plant integrity and personnel safety is maintained, in accordance with workplace procedures, through consultation with appropriate personnel and technical and operational documentation
  18. Appropriate personnel are notified, in accordance with workplace procedures, when defects are detected
  19. Complete documentation