Google Links

Follow the links below to find material targeted to the unit's elements, performance criteria, required skills and knowledge

Elements and Performance Criteria

  1. Prepare to joint and maintain LV underground paper insulated cables
  2. Job requirements and workplace procedures are identified and communicated with relevant personnel
  3. Work health and safety (WHS)/occupational health and safety (OHS), environmental and workplace procedures for the jointing and maintenance of energised LV underground paper insulated cables are obtained and confirmed for the purposes of the work to be performed and
  4. Work is prioritised and sequenced for completion within acceptable timeframes following consultation with relevant personnel and in accordance with workplace procedures
  5. WHS/OHS and environmental hazards are identified, risks are assessed and control measures identified in accordance with workplace procedures
  6. Relevant work permits are obtained, understood and signed in accordance with workplace procedures
  7. Plant, equipment, tools and personal protective equipment (PPE) required for work are identified, obtained and confirmed in working order
  8. Work site is prepared to minimise risk, damage to property, commerce and individuals in accordance with workplace procedures
  9. Carry out jointing and maintenance of energised LV underground paper insulated cables
  10. Requirements for lifting and/or climbing and/or working at heights and the use of power tools/equipment are followed in accordance with workplace procedures
  11. Cables are tested in accordance with workplace procedures
  12. Cables are prepared for jointing, terminating or maintaining in accordance with construction drawings, manufacturer instructions and workplace procedures
  13. Cables are jointed, terminated and maintained in accordance with construction drawings, manufacturer instructions and workplace procedures
  14. Unplanned events are responded to in accordance with workplace procedures
  15. Quality checks of work are undertaken in accordance with workplace procedures
  16. Complete jointing and maintenance of energised LV underground paper insulated cables
  17. WHS/OHS and environmental incidents are reported in accordance with workplace procedures, as required
  18. Tools, equipment and any surplus resources and materials are, where appropriate, cleaned, checked and returned to storage or disposed of in accordance with workplace procedures
  19. Relevant work permits are signed off and energised LV underground paper insulated cables are returned to service in accordance with workplace procedures
  20. Work records, reports and/or documentation are completed in accordance with workplace procedures