  1. Prepare to install and maintain de-energised HV underground polymeric cables
  2. Job requirements and workplace procedures are identified and communicated with relevant personnel
  3. Work health and safety (WHS)/occupational health and safety (OHS), environmental and workplace procedures for the installation and maintenance of de-energised HV underground polymeric cables are obtained and confirmed for the purposes of the work to be performed
  4. Work is prioritised and sequenced for completion within acceptable timeframes following consultation with relevant personnel and in accordance with workplace procedures
  5. WHS/OHS and environmental hazards are identified, WHS/OHS risks are assessed and control measures identified in accordance with workplace procedures
  6. Relevant work permits are confirmed and signed in accordance with workplace procedures
  7. Plant, equipment, tools and personal protective equipment (PPE) required for work are identified, obtained and confirmed in working order
  8. Worksite is prepared to minimise risk, damage to property, commerce and individuals in accordance with workplace procedures
  9. Traffic management plan is confirmed as being applied in accordance with workplace procedures
  10. Carry out the installation and maintenance of de-energised HV underground polymeric cables
  11. Requirements for lifting and/or climbing and/or working at heights and the use of power tools/equipment are followed in accordance with workplace procedures
  12. Systems and circuits are isolated as required, proved safe to work on in accordance with workplace procedures
  13. De-energised HV underground polymeric cables are installed in accordance with the work schedule and workplace procedures
  14. Maintenance, including repair and/or replacement of de-energised HV undergroundpolymeric cables is carried out in accordance with the work schedule and workplace procedures
  15. Unplanned events are responded to in accordance with workplace procedures
  16. Quality checks of work are undertaken in accordance with workplace procedures
  17. Complete installation and maintenance of de-energised HV underground polymeric cables
  18. WHS/OHS and environmental incidents are reported in accordance with workplace procedures, as required
  19. Worksite is rehabilitated, cleaned up and made safe in accordance with workplace procedures
  20. Tools, equipment and surplus resources are, where appropriate, cleaned, checked and returned to storage in accordance with workplace procedures
  21. Relevant work permits are signed off and HV underground polymeric cables are returned to service in accordance with workplace procedures