Elements and Performance Criteria
- Plan and coordinate for the preparation of HV Transmission switching programs
- OHS practices/procedures and environmental and sustainable energy procedures, which may influence the preparation of the switching program, are reviewed and determined.
- Purpose of the switching program is established after data is analysed and expected outcomes of the work are confirmed with the appropriate personnel.
- Established policies, procedures and specifications for the switching program are obtained or established with the appropriate personnel.
- Switching procedures are discussed with and/or directed to the appropriate personnel in order to ascertain the project brief.
- Switching parameters are ascertained from established policies, procedures and specifications.
- Equipment/tools and personal protective equipment are selected based on specified Performance Criteria and established procedures.
- Work roles and tasks are allocated according to requirements and individuals' competencies.
- Work is prioritised and sequenced for the most efficient/effective outcome, completed within an acceptable timeframe to a quality standard and in accordance with established procedures.
- Liaison and communication issues with other/authorised personnel, authorities and clients are resolved and activities coordinated to carry out work.
- Risk control measures are identified, prioritised and evaluated against the work schedule.
- Relevant work permits are secured to coordinate the performance of work according to requirements and/or established procedures.
- Carry out and coordinate the preparation of HV Transmission switching programs
- Circuit/systems modelling is used to evaluate alternative proposals as per established procedures.
- OHS and sustainable energy principles, functionality and practices to reduce the incidents of accidents and minimise waste are incorporated into the project in accordance with requirements and/or established procedures.
- Decisions concerning the preparation of the HV Transmission Switching program are made on the basis of safety and effective outcomes according to requirements and/or established procedures.
- The effectiveness of the finished project is analysed as per requirements and established procedures.
- Technical advice is given regarding potential hazards, safety risks and control measures so that monitoring and preventative action can be undertaken and/or appropriate authorities consulted, where necessary, in accordance with requirements and established procedures.
- Essential knowledge and associated skills are applied to analyse specific data and compare it with compliance specifications to ensure completion of the project within an agreed timeframe according to requirements.
- Testing of the program is undertaken according to requirements and established procedures.
- Work teams/groups are arranged/coordinated/evaluated to ensure planned goals are met according to established procedures.
- Solutions to non-routine problems are identified and actioned, using acquired essential knowledge and associated skills, according to requirements.
- Quality of work is monitored against personal performance agreement and/or established organisational and professional standards.
- Complete and coordinate the preparation of HV Transmission switching programs
- Final review of the switching program is undertaken to ensure it complies with all requirements and include all specifications and documentations needed to complete the project.
- Appropriate personnel are notified of completion and reports and/or completion documents are finalised/commissioned.
- Reports and/or completion documents are submitted to relevant personnel/organisations for approval and, where applicable, statutory or regulatory approval.
- Approved copies of switching program documents are issued and records are updated in accordance with established procedures.