Unit of Competency Mapping – Information for Teachers/Assessors – Information for Learners

UETTDRDP15 Mapping and Delivery Guide
Inspect, maintain and restore energised low voltage overhead distribution network infrastructure

Version 1.0
Issue Date: June 2024


Qualification -
Unit of Competency UETTDRDP15 - Inspect, maintain and restore energised low voltage overhead distribution network infrastructure
Description
Employability Skills
Learning Outcomes and Application This unit covers the inspection of overhead structures, such as poles and/or other structures other than towers, and the maintenance of overhead energised low voltage (LV) conductors and cables. It includes the conducting of LV switching operations involving the operation of circuit breaking and isolation devices from a given switching schedule in accordance with enterprise procedures. It covers LV distribution systems in field situations but also includes paralleling in accordance with the switching schedule. It also includes inspection of electrical apparatus, such as overhead conductors and or cables, underground and overhead transition points, electrical equipment, such as pole-mounted transformers, switchgear, hardware and/or earthing systems. It encompasses the completion of inspection reports and other relevant documentation in accordance with requirements.The application of the skills and knowledge described in this unit requires a licence/registration to practice in the workplace subject to regulations for undertaking of electrical work. Other conditions may apply under state and territory legislative and regulatory licencing requirements which must be confirmed prior to commencing this unit.
Duration and Setting X weeks, nominally xx hours, delivered in a classroom/online/blended learning setting.
Prerequisites/co-requisites
Competency Field Distribution
Development and validation strategy and guide for assessors and learners Student Learning Resources Handouts
Activities
Slides
PPT
Assessment 1 Assessment 2 Assessment 3 Assessment 4
Elements of Competency Performance Criteria              
Element: Prepare for the inspection, maintenance and restoration of overhead distribution network infrastructure
  • Works schedule(s), including drawings, plans, requirements, established procedures and material lists, are received, analysed and confirmed, as necessary, by site inspection
       
Element: Relevant requirements and established procedures for the work are communicated to all personnel and identified for all worksites
       
Element: Work health and safety (WHS)/occupational health and safety (OHS) policies and procedures related to requirements and established procedures for the inspection of overhead structures and electrical apparatus used on poles and/or structures, the maintenance of overhead energised LV conductors and cables and LV switching, are obtained and confirmed for the purposes of the work to be performed and communicated
       
Element: Physical loads and calculations are confirmed according to requirements using essential knowledge and appropriate skill
       
Element: Work is prioritised and sequenced following consultation with others for completion within acceptable timeframes and in accordance with established procedures
       
Element: Hazards are identified, WHS/OHS risks assessed and control measures prioritised, implemented and monitored, including emergency exits kept clear according to established procedures
       
Element: Relevant work permits are obtained to access and perform work according to requirements and/or established procedures
       
Element: Resources, including personnel, equipment, tools and personal protective equipment (PPE), required for the job are obtained and confirmed in working order
       
Element: Specialist equipment for live work is inspected and confined in working order in accordance with requirements and established procedures
       
Element: Relevant personnel at worksite are confirmed current in first aid, pole top rescue and other related work procedures according to requirements
       
Element: Liaison and communication issues with other/authorised personnel, authorities, clients and land owners are resolved to carry out work where necessary
       
Element: Site is prepared according to the work schedule and to minimise risk and damage to property, commerce and individuals in accordance with established procedures
       
Element: Personnel participating in the work, including plant operators and contractors, are fully briefed and respective responsibilities confirmed, where applicable, in accordance with established procedures
       
Element: Traffic management plan is identified and implemented
       
Element: Carry out inspection, maintenance and restoration of overhead distribution network infrastructure
  • WHS/OHS, sustainable energy and environmental principles and practices to reduce the incidents of accidents and minimise waste are monitored and followed in accordance with requirements and/or established procedures
       
Element: Lifting, climbing, working in confined spaces and aloft, and use of power tools/equipment, techniques and practices are safely followed, and currency according to requirements confirmed
       
Element: Essential knowledge and associated skills are applied in the safe maintenance and restoration of overhead distribution network infrastructure to ensure completion in an agreed timeframe and to quality standards with a minimum of waste according to requirements
       
Element: Inspection of overhead structures and electrical apparatus used on poles and/or structures is carried out in accordance with the work schedule and requirements/established procedures
       
Element: Maintenance, including repair and/or replacement of poles and/or structures, is carried out in accordance with the work schedule and requirements/established procedures
       
Element: Communications with Switching Control Officer are established and maintained throughout the isolation operation according to established procedures
       
Element: Electrical equipment and associated circuits line/network or worksite to be switched, including paralleling, is isolated and proved de-energised using appropriate devices and earthed, where required, according to requirements and established procedures
       
Element: Hazard warnings and safety signs are recognised and hazards and assessed WHS/OHS risks are reported to the immediate authorised persons for directions according to established procedures
       
Element: Unplanned events during the inspection, maintenance or switching procedures are undertaken within the scope of established procedures
       
Element: Known solutions to a variety of problems are applied using acquired essential knowledge and associated skills
       
Element: Ongoing checks of quality of the work are undertaken in accordance with instructions and established procedures
       
Element: Complete the inspection, maintenance and restoration of overhead distribution network infrastructure
  • Work undertaken is checked against works schedule for conformance with requirements and anomalies reported in accordance with established procedures
       
Element: Accidents and/or injuries are reported in accordance with requirements/established procedures, where applicable
       
Element: Worksite is rehabilitated, cleaned up and made safe in accordance with established procedures
       
Element: Tools, equipment and any surplus resources and materials are, where appropriate, cleaned, checked and returned to storage or disposed of in accordance with established procedures
       
Element: Relevant work permits are signed off and overhead structures and electrical apparatus used on poles and/or structures are returned to service in accordance with requirements
       
Element: Works completion records, reports, as installed/modified drawing and/or documentation and information are finalised and processed and appropriate personnel notified
       

Submission Requirements

List each assessment task's title, type (eg project, observation/demonstration, essay, assignment, checklist) and due date here

Assessment task 1: [title]      Due date:

(add new lines for each of the assessment tasks)


Assessment Tasks

Copy and paste from the following data to produce each assessment task. Write these in plain English and spell out how, when and where the task is to be carried out, under what conditions, and what resources are needed. Include guidelines about how well the candidate has to perform a task for it to be judged satisfactory.

Range is restricted to essential operating conditions and any other variables essential to the work environment.

Non-essential conditions may be found in the Companion Volume Implementation Guide.

Copy and paste from the following performance criteria to create an observation checklist for each task. When you have finished writing your assessment tool every one of these must have been addressed, preferably several times in a variety of contexts. To ensure this occurs download the assessment matrix for the unit; enter each assessment task as a column header and place check marks against each performance criteria that task addresses.

Observation Checklist

Tasks to be observed according to workplace/college/TAFE policy and procedures, relevant legislation and Codes of Practice Yes No Comments/feedback
Works schedule(s), including drawings, plans, requirements, established procedures and material lists, are received, analysed and confirmed, as necessary, by site inspection 
 
 
 
 
 
 
 
 
 
 
 
 
 
WHS/OHS, sustainable energy and environmental principles and practices to reduce the incidents of accidents and minimise waste are monitored and followed in accordance with requirements and/or established procedures 
 
 
 
 
 
 
 
 
 
 
Work undertaken is checked against works schedule for conformance with requirements and anomalies reported in accordance with established procedures 
 
 
 
 
 

Forms

Assessment Cover Sheet

UETTDRDP15 - Inspect, maintain and restore energised low voltage overhead distribution network infrastructure
Assessment task 1: [title]

Student name:

Student ID:

I declare that the assessment tasks submitted for this unit are my own work.

Student signature:

Result: Competent Not yet competent

Feedback to student

 

 

 

 

 

 

 

 

Assessor name:

Signature:

Date:


Assessment Record Sheet

UETTDRDP15 - Inspect, maintain and restore energised low voltage overhead distribution network infrastructure

Student name:

Student ID:

Assessment task 1: [title] Result: Competent Not yet competent

(add lines for each task)

Feedback to student:

 

 

 

 

 

 

 

 

Overall assessment result: Competent Not yet competent

Assessor name:

Signature:

Date:

Student signature:

Date: