Application
This unit of competency supports the role of those who deliver concrete placing booms to residential, commercial or civil construction sites.
Prerequisites
Apply OHS requirements, policies and procedures in the construction industry |
Elements and Performance Criteria
1 | Plan and prepare. | 1.1 | Work instructions, work health and safety (WHS) requirements and other information relevant to the work are identified, confirmed and applied for planning and preparation purposes. |
1.2 | Tools and equipment consistent with job requirements are selected and checked for serviceability, and faults are rectified and reported before work begins. | ||
1.3 | Materials appropriate to the work application are identified, obtained, prepared, safely handled and located ready for use. | ||
1.4 | Environmental requirements are identified for the project according to environmental plans, local council requirements and regulatory obligations. |
2 | Conduct boom delivery system pre-operational checks. | 2.1 | Pre-start, start-up, park and shut-down procedures, including emergency shut-down procedures, are carried out on the vehicle and pump according to manufacturer and/or site-specific requirements. |
2.2 | Vehicle controls and functions are checked for serviceability and faults are rectified and reported in vehicle log book. | ||
2.3 | Distribution system components are checked before use. | ||
2.4 | Hoppers are cleaned and serviced prior to use. |
3 | Operate concrete boom delivery vehicle. | 3.1 | Hazards associated with vehicle positioning and operations are identified and safe operating techniques are used to minimise risk. |
3.2 | Engine power is managed to ensure efficiency of concrete pump vehicle platform movements and to minimise damage to engine and gears. | ||
3.3 | Engine power is coordinated with gear selection ensuring smooth transition and operation within torque range. | ||
3.4 | Truck is operated to work instructions according to company operating procedures. | ||
3.5 | Road and traffic conditions are monitored, taking into account road standards, traffic flow, distance and load, and ensuring no injury to people or damage to property, equipment, loads and facilities. | ||
3.6 | Truck is brought to a halt smoothly, using the engine retarder, gears and brakes, and minimising wear and tear on vehicle. |
4 | Deliver concrete. | 4.1 | Hazards associated with positioning and operating boom delivery components are identified and analysed, and safe operating techniques are used to minimise risk. |
4.2 | Boom delivery vehicle is positioned at site where it can best service the delivery task and provide access to concrete supply vehicles. | ||
4.3 | Delivery platform stabilisers are prepared, deployed and checked to manufacturer requirements for operation and safety. | ||
4.4 | Delivery system components are positioned securely and safely, according to manufacturer specifications, and checked prior to use. | ||
4.5 | Pumping systems are test run and prepared for use according to equipment specifications. | ||
4.6 | Supply of bulk concrete mix to the hopper is coordinated safely with supply vehicle operators. | ||
4.7 | Boom delivery system is operated and its positioning is varied to maintain concrete delivery to the required destination. | ||
4.8 | Boom delivery system is safely withdrawn at completion of delivery task. |
5 | Carry out operator maintenance. | 5.1 | Boom delivery vehicle is safely parked, prepared for maintenance and shut down as per manufacturer manual and organisational requirements. |
5.2 | Inspection and fault finding on the vehicle, pump and boom system components are conducted according to manufacturer specifications, with outcomes recorded according to workplace procedures. | ||
5.3 | Defective parts are removed and replaced safely and effectively according to manufacturer manual and organisational requirements. | ||
5.4 | Regular programmed maintenance tasks are carried out according to manufacturer and organisational requirements. |
6 | Clean up. | 6.1 | Work area is cleared and materials disposed of, reused or recycled according to project environmental management plan. |
6.2 | Vehicle, tools and equipment are cleaned, checked, maintained and stored according to manufacturer recommendations and standard work practices. |
Required Skills
Required skills |
learning skills to: evaluate own actions and make judgments about performance and necessary improvements respond to change, such as differences in work site, and environmental and quality requirements numeracy skills to check levels of lubricants in tools oral communication skills to: enable clear and direct communication, using questioning to identify and confirm requirements, and share information report work site hazards to appropriate personnel, including faults in tools, equipment or materials use language and concepts appropriate to cultural differences reading skills to: interpret documentation, including drawings and specifications understand written instructions, procedures and signage interpret manufacturer instructions for safely handling tools and equipment writing skills to complete pre-operational checklists and equipment fault forms |
Required knowledge |
boom and line establishment techniques characteristics, technical capabilities and limitations of concrete boom delivery vehicle systems: operational, maintenance and basic diagnostic procedures pumps and pumping system operations safe operating techniques in all terrain construction activity sequences relating to bulk concreting operations general construction terminology quality requirements relating to concrete boom delivery operations requirements and methods for safe materials handling site and equipment safety requirements: knowing when and how to activate emergency shut-down procedures overhead safety requirements relating to boom operations site isolation and traffic control responsibilities and authorities state or territory regulatory requirements relating to boom delivery system operations types, location and usage of relevant safety information: job safety analyses (JSA) and safe work method statements (SWMS) safety data sheets(SDS) safety manuals and instructions for plant, tools and equipment signage environmental and work site safety plans |
Evidence Required
The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package. | |
Overview of assessment | This unit of competency could be assessed by undertaking a range of tasks in the workplace or a close simulation of the workplace environment, provided that simulated or project-based assessment techniques fully replicate construction workplace conditions, materials, activities, responsibilities and procedures. |
Critical aspects for assessment and evidence required to demonstrate competency in this unit | A person should demonstrate the ability to: conduct concrete boom delivery truck system operations over not less than three shifts at two different sites, which will include demonstration of: positioning of the vehicle preparation and positioning of the booms and lines preparation of the pump and hopper coordination of maintenance of hopper levels delivery of concrete to required location on work site variation of boom delivery system positioning to meet changing requirements withdrawal of the boom delivery system application of emergency procedures authorised operator maintenance locate, interpret and apply relevant information, standards and specifications relating to concrete boom delivery operations comply with site safety plans and procedures comply with organisational policies and procedures, relating to concrete boom delivery operations, including quality requirements communicate and work effectively and safely with others during each stage of the concrete boom delivery operation. |
Context of and specific resources for assessment | Assessment of this unit: must be in the context of the work environment may be conducted in an off-site context, provided it is realistic and sufficiently rigorous to cover all aspects of workplace performance, including task skills, task management skills, contingency management skills and job role environment skills must meet relevant compliance requirements. Resource implications for assessment include: an induction procedure realistic tasks or simulated tasks covering the mandatory task requirements tools and equipment appropriate to applying safe work practices support materials appropriate to activity workplace instructions relating to safe work practices and addressing hazards and emergencies safety data sheets. |
Method of assessment | Assessment for this unit must verify the practical application of the required skills and knowledge, using a combination of the following methods: direct observation of tasks in real or simulated work conditions questioning to confirm the ability to consistently identify and correctly interpret the essential underpinning knowledge required for practical application review of relevant authenticated documentation from third parties, such as existing supervisors, team leaders or specialist training staff. |
Guidance information for assessment | This unit could be assessed on its own or in combination with other units relevant to the job function. Reasonable adjustments for people with disabilities must be made to assessment processes where required. This could include access to modified equipment and other physical resources, and the provision of appropriate assessment support. Assessment processes and techniques should, as far as is practical, take into account the language, literacy and numeracy capacity of the candidate in relation to the competency being assessed. |
Range Statement
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included. | |
Work health and safety requirements must comply with state and territory legislation and regulations and project safety plan, and may include: | assistance of others or the use of manual or mechanical lifting devices with handling activities where size, weight or other issues, such as disability, are a factor emergency procedures, including extinguishing fires, organisational first aid requirements, and evacuation procedures hazard control hazardous materials and substances personal protective equipment (PPE) prescribed under legislation, regulations and workplace policies and practices safe operating procedures, including the conduct of operational risk assessment and treatments associated with: earth leakage boxes lighting power cables, including overhead service trays, cables and conduits signage and restricted access barriers surrounding structures traffic control trip hazards work site visitors and the public working at heights working in confined spaces working in proximity to others working outdoors in warm climates use of firefighting equipment use of tools and equipment workplace environmental requirements and safety. |
Information may include: | diagrams or sketches instructions issued by authorised organisational and external personnel memos regulatory and legislative requirements relating to concrete boom delivery relevant Australian standards safe work procedures relating to concrete boom delivery safety data sheets signage vehicle systems operations and the environment verbal, written and graphical instructions, including manufacturer specifications and instructions where specified work bulletins work schedules, plans and specifications. |
Planning and preparation must include: | assessing conditions and hazards determining work requirements and safety plans and procedures identifying and rectifying equipment defects inspecting work sites. |
Environmental requirements may include: | designation of a pump washout area clean-up management dust suppression, noise and fume abatement stormwater management vibration management waste management. |
Functions must include: | brakes manoeuverability steering. |
System components must include: | adaptors boom components hoses lines. |
Hazards associated with vehicle positioning and operations may | interruption of concrete flow mechanical failure of vehicle or parts positioning hazards: insufficient clearance space between trucks and equipment placing vehicle and pump on sloping or unstable ground proximity of vehicle to trenches traffic-related hazards. |
Hazards associated with positioning and operating boom may | mechanical failure of the boom proximity to overhead power lines or electrical equipment traffic-related hazards. |
Concrete delivery systems: | must include: boom-mounted conveyors lines may include adaptors. |
Concrete mixes vary in water content and, in order from wet to dry, include: | block-fill pool-mix topping slab footing curb and guttering. |
Operator maintenance: | must include: authorised servicing cleaning monitoring, recording and reporting faults may include: conducting authorised minor replacements providing assistance to maintenance personnel during maintenance and repair activities. |
Sectors
Concreting
Employability Skills
This unit contains employability skills.
Licensing Information
Licensing, legislative, regulatory or certification requirements apply to concreting work in different states and territories. Candidates are advised to consult with the relevant regulatory authorities.