UETTDRSB38
Commission power system distribution field devices


Application

This unit covers the commissioning of automatic circuit reclosers (ACRs), gas switches, regulators and line capacitors; and communication systems, including mobile phones and trunked mobile radio (TMR). It also includes communication with the operating authority, testing, clearing after testing and energising using techniques that are acceptable to the operating authority.

The application of the skills and knowledge described in this unit requires a licence/registration to practice in the workplace subject to regulations for undertaking of electrical work.

Other conditions may apply under state and territory legislative and regulatory licencing requirements which must be confirmed prior to commencing this unit.


Elements and Performance Criteria

ELEMENTS

PERFORMANCE CRITERIA

Elements describe the essential outcomes.

Performance criteria describe the performance needed to demonstrate achievement of the element.

1

Plan for the commissioning of distribution field devices

1.1

Work schedules, including drawings, plans, requirements, procedures and material lists, are acquired, analysed and the extent of work determined

1.2

Relevant requirements and established procedures for the work are communicated to all personnel and identified for all worksites

1.3

Hazards are identified, work health and safety (WHS)/occupational health and safety (OHS) risks assessed and control measures prioritised, implemented and monitored, including emergency exits kept clear, to ensure safe systems of work are followed and according to established procedures

1.4

Work is prioritised and sequenced for the most efficient and effective outcome following consultation with others for completion within acceptable timeframes, to agreed quality standards and in accordance with established policies and procedures

1.5

Resources, including personnel, equipment, tools and personal protective equipment (PPE), required for the job are identified, acquired and confirmed safe and in technical working order

1.6

Liaison issues with other personnel and/or authorities are resolved and activities coordinated to facilitate the work

1.7

Personnel participating in the work, including plant operators and contractors, are fully briefed, their respective responsibilities explained and coordinated, and appropriate authorisation checked in accordance with established procedures

1.8

Worksite is prepared according to the work schedule and to minimise risk and damage to property and personnel in accordance with established procedures

2

Carry out the commissioning of distribution network field devices

2.1

WHS/OHS and sustainable energy principles and practices to reduce the incidence of accidents and minimise waste are implemented and monitored in accordance with established procedures

2.2

Cardiopulmonary resuscitation (CPR), rescue from live electrical apparatus and other related safety procedures are in place according to requirements and established procedures

2.3

Safe working documentation is acquired and requirements completed in accordance with established procedures

2.4

Lifting, use of power tools/equipment techniques and practices are safely exercised in accordance with established procedures

2.5

Hazard warnings and safety signs are recognised and hazards and assessed WHS/OHS risks monitored and preventive action taken and/or appropriate authorities consulted, where necessary, in accordance with established procedures

2.6

Commissioning, including testing of distribution field devices, is undertaken according to requirements and established procedures

2.7

Data is analysed and compared with compliance specifications to ensure completion of the maintenance work is within an agreed timeframe and according to requirements

2.8

Essential knowledge and associated skills are applied for the safe commissioning of distribution network field devices to ensure completion in an agreed timeframe and to quality standards with a minimum of waste according to requirements

2.9

Unplanned events or conditions are responded to in accordance with established procedures

3

Complete the commissioning of distribution network field devices

3.1

Functional checks of distribution field devices are completed and all work checked against the requirements to ensure compliance

3.2

Anomalies between the work schedule requirements and measured performance are reported and solutions identified in accordance with established procedures

3.3

Safe working documentation is surrendered and transformer made ready for service

3.4

Worksite is rehabilitated, cleaned up and confirmed safe in accordance with established procedures

3.5

Tools, equipment and any surplus resources and materials are cleaned, checked and returned to storage in accordance with established procedures

3.6

Documents and records related to the distribution field devices are updated in accordance with established procedures

Foundation Skills

Foundation skills essential to performance are explicit in the performance criteria of this unit of competency.


Range Statement

Range is restricted to essential operating conditions and any other variables essential to the work environment.

Non-essential conditions may be found in the Companion Volume Implementation Guide.


Sectors

Not applicable.


Competency Field

Substation