The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Plan and prepare to inspect site preparation and foundations and footings.
|
|
Site classification is determined according to BCA definitions and compliance requirements for site preparation, foundations and footings are identified and interpreted. Completed |
Evidence:
|
Approved building design drawings and specifications are interpreted and variations from deemed-to-satisfy provisions for compliance are confirmed with senior personnel or statutory authority. Completed |
Evidence:
|
Inspection is scheduled according to project and legislative and regulatory requirements, and stakeholders are notified as required. Completed |
Evidence:
|
Missed inspections are recorded and reported according to legislative and regulatory requirements. Completed |
Evidence:
|
Work health and safety (WHS) requirements for inspections of site preparations, foundations and footings are identified. Completed |
Evidence:
|
Inspect and report on site preparation, foundations and footings.
|
|
Site preparation, foundations and footings are surveyed according to project, statutory and WHS requirements. Completed |
Evidence:
|
Features of site preparation, foundations and footings are assessed against compliance requirements, approved drawings, and discussed with on-site personnel as required. Completed |
Evidence:
|
Inspections undertaken to ensure compliance with waterproofing are validated and documented. Completed |
Evidence:
|
Details of non-compliant features are documented and reported according to workplace procedures and legislative and regulatory requirements. Completed |
Evidence:
|
Non-compliant features are discussed with relevant contractors and work required to remedy non-compliance is negotiated according to scope of personal responsibilities. Completed |
Evidence:
|
Timeframe for remedial action and rescheduled inspection is negotiated according to scope of personal responsibilities, and contractor’s failure to comply is reported according to legislative and regulatory requirements if required. Completed |
Evidence:
|
Certificate of compliance for foundations and footings is prepared and processed according to legislative and regulatory requirements and scope of personal responsibilities. Completed |
Evidence:
|
Plan and prepare to inspect structural provisions.
|
|
Extreme weather events for the area are determined and compliance requirements for structural provisions are identified and interpreted. Completed |
Evidence:
|
Approved building design drawings and specifications are interpreted and variations from deemed-to-satisfy provisions for compliance are confirmed with senior personnel or statutory authority. Completed |
Evidence:
|
Inspection is scheduled according to project and legislative and regulatory requirements, and stakeholders are notified as required. Completed |
Evidence:
|
Missed inspections are recorded and reported according to legislative and regulatory requirements. Completed |
Evidence:
|
WHS requirements for inspections of structural provisions are identified. Completed |
Evidence:
|
Inspect and report on structural provisions.
|
|
Structural provisions are inspected according to project, statutory and WHS requirements. Completed |
Evidence:
|
Features of structural provisions are assessed against compliance requirements and approved drawings, and discussed with on-site personnel as required. Completed |
Evidence:
|
Details of non-compliant features are documented and reported according to workplace procedures and legislative and regulatory requirements. Completed |
Evidence:
|
Non-compliant features of structural provisions are discussed with relevant contractors and work required to remedy non-compliance is negotiated according to scope of personal responsibilities. Completed |
Evidence:
|
Timeframe for remedial action and rescheduled inspection is negotiated according to scope of personal responsibilities, and contractor’s failure to comply is reported according to legislative and regulatory requirements if required. Completed |
Evidence:
|
Certificate of compliance for structural provisions is prepared and processed according to legislative and regulatory requirements and scope of personal responsibilities. Completed |
Evidence:
|
Plan and prepare to inspect wet areas.
|
|
Wall and substrate construction methods and materials are identified. Completed |
Evidence:
|
Compliance requirements for waterproofing are identified and interpreted. Completed |
Evidence:
|
Approved building design drawings and specifications are interpreted and variations from deemed-to-satisfy provisions for compliance are confirmed with senior personnel or statutory authority. Completed |
Evidence:
|
Inspection is scheduled according to project and legislative and regulatory requirements, and stakeholders are notified as required. Completed |
Evidence:
|
Missed inspections are recorded and reported according to legislative and regulatory requirements. Completed |
Evidence:
|
WHS requirements for inspections of wet areas are identified. Completed |
Evidence:
|
Inspect and report on wet areas.
|
|
Wet areas are inspected according to project, statutory and WHS requirements. Completed |
Evidence:
|
Waterproofing installation is assessed against manufacturer specifications, compliance requirements and approved drawings and discussed with on-site personnel as required. Completed |
Evidence:
|
Details of non-compliant features are documented and reported according to workplace procedures and legislative and regulatory requirements. Completed |
Evidence:
|
Non-compliant features of wet areas are discussed with relevant contractors and work required to remedy non-compliance is negotiated according to scope of personal responsibilities. Completed |
Evidence:
|
Timeframe for remedial action and rescheduled inspection is negotiated according to scope of personal responsibilities, and contractor’s failure to comply is reported according to legislative and regulatory requirements if required. Completed |
Evidence:
|
Certificate of compliance for wet areas is prepared and processed according to legislative and regulatory requirements and scope of personal responsibilities. Completed |
Evidence:
|