The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Prepare to inspect the erection of prefabricated concrete elements.
|
|
Check the prefabricated concrete element records to ascertain progress and prepare for the physical inspection of the prefabricated concrete elements. Completed |
Evidence:
|
Check prefabricated concrete element records to ensure that safe systems of work and safe work practices have been enforced and followed. Completed |
Evidence:
|
Check prefabricated concrete element manufacturing and inspection records to confirm design specifications have been followed in accordance with AS 3850 Prefabricated concrete elements during manufacture, storage, lifting and handling through to installation and final fixing. Completed |
Evidence:
|
Conduct inspection of the erection of prefabricated concrete elements.
|
|
Inspect safety systems and ensure that workers and contractors are following safety requirements during the erection of the prefabricated concrete elements. Completed |
Evidence:
|
Inspect placement and storage arrangements of prefabricated concrete elements onsite and ensure they conform to the erection documentation as detailed in AS 3850 Prefabricated concrete elements. Completed |
Evidence:
|
Inspect processes to ensure erection areas are cleared, exclusion zones set up, barriers erected, and site personnel advised of restricted access areas prior to erection of prefabricated concrete elements. Completed |
Evidence:
|
Inspect and confirm that fixings supplied for attachments to the permanent structure and for temporary supports comply with the requirements of the erection documentation approved by relevant personnel, AS 3850 Prefabricated concrete elements and the project specifications. Completed |
Evidence:
|
Inspect and confirm that temporary supports, dowels and shims are correctly placed, and components positioned in accordance with the erection documentation as detailed in AS 3850 Prefabricated concrete elements and project specifications. Completed |
Evidence:
|
Inspect prefabricated concrete element stability.
|
|
Inspect and confirm that the erected prefabricated concrete elements comply with the erection documentation approved by relevant personnel as detailed in AS 3850 Prefabricated concrete elements and engineering specifications. Completed |
Evidence:
|
Inspect and confirm that fixtures between structural steel components and temporarily supported elements comply with the erection documentation approved by relevant personnel and as detailed in AS 3850 Prefabricated concrete elements and engineering specifications. Completed |
Evidence:
|
Inspect and confirm that all grouting, including breathers and grout tubes, are sufficiently filled and gained suitable strength. Completed |
Evidence:
|
Ensure that temporary supports are removed and/or moved, re-positioned or replaced only with the written approval of the project design engineer in accordance with AS 3850 Prefabricated concrete elements. Completed |
Evidence:
|
Oversee the safe removal of temporary bracing, plant and equipment from site. Completed |
Evidence:
|
Check if damage has occurred and if so, identify and consult the appropriate person to arrange for repair. Completed |
Evidence:
|
Inspect the completion of the erection work and clearing and cleaning of work areas prior to other trades being permitted to enter work zones. Completed |
Evidence:
|
Inspect and confirm that all grouting, including breathers and grout tubes, are sufficiently filled and gained suitable strength. |
|
Completed |
Evidence:
|
Oversee the safe removal of temporary bracing, plant and equipment from site. |
|
Completed |
Evidence:
|
Check if damage has occurred and if so, identify and consult the appropriate person to arrange for repair. |
|
Completed |
Evidence:
|
Inspect the completion of the erection work and clearing and cleaning of work areas prior to other trades being permitted to enter work zones. |
|
Completed |
Evidence:
|