The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Prepare to construct underground work
|
|
Obtain construction design plan from appropriate personnel to scope the work and arrange for site access Completed |
Evidence:
|
Notify appropriate personnel of identified safety hazards and other services Completed |
Evidence:
|
Obtain plant, tools and safety equipment to perform tasks safely and efficiently Completed |
Evidence:
|
Determine the type of undergroundenclosure specified in the construction design plan that is required for the project Completed |
Evidence:
|
Install enclosure
|
|
Use tools according to enterprise guidelines and occupational health and safety (OHS) regulations Completed |
Evidence:
|
Place a foundation of suitable material to provide a safe and stable footing prior to installing an underground enclosure in an excavation Completed |
Evidence:
|
Place a recognised barrier over the construction where an enclosure is to be installed over power cables according to enterprise requirements or agreements with other authorities Completed |
Evidence:
|
Install an enclosure specified in the construction design plan to manufacturer's specifications using the specified materials Completed |
Evidence:
|
Install an earth mat facility under the enclosure where specified and required by the enterprise Completed |
Evidence:
|
Install connecting pipe works
|
|
Install conduit in trench to enterprise specifications Completed |
Evidence:
|
Connect conduit to an enclosure according to manufacturer's specification and industry practice Completed |
Evidence:
|
Complete project
|
|
Complete reports according to enterprise policy and record alterations to plans using appropriate symbols Completed |
Evidence:
|
Recover obsolete materials and equipment and return to appropriate point for disposal Completed |
Evidence:
|
Restore site according to the requirements of enterprise or approving authority and to customer satisfaction Completed |
Evidence:
|
Notify appropriate personnel of job completion and obtain sign off Completed |
Evidence:
|