The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Determine job requirements
|
|
Follow standard operating procedures (SOPs) Completed |
Evidence:
|
Comply with work health and safety (WHS) requirements at all times |
|
Completed |
Evidence:
|
Use appropriate personal protective equipment (PPE) in accordance with SOPs |
|
Completed |
Evidence:
|
Identify job requirements from specifications, drawings, job sheets or work instructions |
|
Completed |
Evidence:
|
Determine the operating conditions of vapour compression systems
|
|
Determine the actual and specified range of operating conditions from measured and calculated values using established procedures to determine as they apply to particular vapour compression systems Completed |
Evidence:
|
Establish operating conditions and record on commissioning documentation |
|
Completed |
Evidence:
|
Obtain tools, equipment and testing devices needed to determine the basic operating conditions and check for correct operation and safety |
|
Completed |
Evidence:
|
Recover refrigerants from split air conditioning systems
|
|
Check for, and protect site from, ignition sources if R32 or other flammable refrigerants are used Completed |
Evidence:
|
Isolate circuits/appliances in strict accordance with work health and safety (WHS) requirements and procedures, where necessary |
|
Completed |
Evidence:
|
Remove refrigerants safely into suitably labelled containers in accordance with legislative and industry requirements |
|
Completed |
Evidence:
|
Deal with contaminated refrigerant in accordance with requirements |
|
Completed |
Evidence:
|
Pressure and leak test split air conditioning systems
|
|
Identify and note safety hazards and implement established risk control measures Completed |
Evidence:
|
Follow industry codes of practice and manufacturer installation instructions |
|
Completed |
Evidence:
|
Take precautions to prevent damage to components while pressure testing the system |
|
Completed |
Evidence:
|
Conduct pressure testing at a pressure compatible with the refrigerant to be used |
|
Completed |
Evidence:
|
Located leak, isolate and repair using methods appropriate to the system type under test and in accordance with industry practices |
|
Completed |
Evidence:
|
Evacuate split air conditioning systems
|
|
Note safety hazards which have not previously been identified, and implement established risk control measures Completed |
Evidence:
|
Evacuate the system to the required level and clean the system of all moisture and other containments in accordance with requirements |
|
Completed |
Evidence:
|
Apply a standing vacuum test in accordance with industry codes of practice and applicable standards |
|
Completed |
Evidence:
|
Charge split air conditioning systems
|
|
Select correct refrigerant for the system, in accordance with manufacturer requirements and industry practices Completed |
Evidence:
|
Measure the refrigerant charge by weight in accordance with manufacturer specifications |
|
Completed |
Evidence:
|
Charge the system in accordance with manufacturer requirements and industry practices |
|
Completed |
Evidence:
|
Check all components and maintain in accordance with manufacturer requirements |
|
Completed |
Evidence:
|
Test the operation of split air conditioning systems
|
|
Start and operate the system Completed |
Evidence:
|
Carry out standard tests to confirm system performance to manufacturer specifications |
|
Completed |
Evidence:
|
Check the refrigerant charge and add refrigerant, if required |
|
Completed |
Evidence:
|
Record test data, as required |
|
Completed |
Evidence:
|
Complete the commissioning/ recommissioning of split air conditioning systems
|
|
Ensure the worksite is cleaned and left in presentable condition in accordance with original presentation, client requirements, industry standards and organisational requirements Completed |
Evidence:
|
Undertake final inspections to ensure installation conforms to industry, legislative and work order requirements |
|
Completed |
Evidence:
|
Instruct the client on the use of the product in accordance with organisational requirements and manufacturer specifications |
|
Completed |
Evidence:
|
Complete certificates of compliance and other relevant commissioning documentation and process in accordance with state/territory regulatory requirements |
|
Completed |
Evidence:
|
Decommission split air conditioning systems
|
|
Electrically disconnect plug in appliance Completed |
Evidence:
|
Recover refrigerants, store and dispose of in accordance with legislative and industry requirements |
|
Completed |
Evidence:
|
Remove units and components and dispose of safely and in accordance with regulations, industry codes of practice and sustainable environmental practices |
|
Completed |
Evidence:
|
Clean the worksite and leave in presentable condition, to client and organisational requirements, industry standards and sustainable environmental practices |
|
Completed |
Evidence:
|
Complete decommissioning documentation and process in accordance with state/territory regulatory requirements |
|
Completed |
Evidence:
|