The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Identify scope of HVACR system work requirements
|
|
Review HVACR system drawings, manufacturer manuals and other technical data for system specifications Completed |
Evidence:
|
Determine HVACR system performance requirements Completed |
Evidence:
|
Determine if any commissioning or modification actions are required to ensure performance requirements are met Completed |
Evidence:
|
Determine relevant regulatory requirements Completed |
Evidence:
|
Inspect site and any existing HVACR equipment to confirm or determine suitability, availability of other services and control requirements Completed |
Evidence:
|
Produce or review HVACR system management schedule including any required installation, commissioning, and modification or maintenance requirements Completed |
Evidence:
|
Integrate building management systems (BMS) considerations into the schedule based on work requirements Completed |
Evidence:
|
Brief team on HVACR system work requirements
|
|
Distribute and discuss drawings, schedules, and major materials and equipment with team Completed |
Evidence:
|
Arrange for required request for further information (RFIs) with designers Completed |
Evidence:
|
Brief team on key compliance and risk factors, including regulatory, work health and safety (WHS) and environmental requirements Completed |
Evidence:
|
Agree with team on critical control points and reporting requirements Completed |
Evidence:
|
Commence installation, commissioning, modification or maintenance tasks
|
|
Supervise any equipment shutdowns required for task Completed |
Evidence:
|
Confirm availability of equipment components and materials for scheduled tasks. Completed |
Evidence:
|
Check and determine that supply of services to work are adequate for task commencement Completed |
Evidence:
|
Ensure all tradespersons have correct drawings Completed |
Evidence:
|
Monitor progress and deal with contingencies
|
|
Establish procedures to ensure work is completed to design specifications Completed |
Evidence:
|
Ensure electrical and HVACR control systems and circuits are consistent with specifications and regulations Completed |
Evidence:
|
Identify problems and contingencies and establish and rectify root cause Completed |
Evidence:
|
Finalise HVACR system work requirements
|
|
Conduct final check to ensure completed work is consistent with drawings, manufacturer manuals and any regulatory requirements Completed |
Evidence:
|
Conduct test run of equipment and system Completed |
Evidence:
|
Identify and correct any malfunctions or errors in required output. Completed |
Evidence:
|
Conduct handover and finalise documentation
|
|
Brief client and operators on machine or equipment operation after completion of work Completed |
Evidence:
|
Prepare and submit required reports in accordance with organisational procedures Completed |
Evidence:
|