The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Plan and prepare
|
|
Access, interpret and apply compliance documentation relevant to the work activity Completed |
Evidence:
|
Obtain, confirm and apply work instructions, including plans, specifications, quality requirements and operational details to the allotted task Completed |
Evidence:
|
Obtain and confirm safety requirements from the site safety plan and organisational policies and procedures, and apply to the allotted task Completed |
Evidence:
|
Identify, obtain and implement signage requirements from the project traffic management plan Completed |
Evidence:
|
Select plant, tools and equipment to carry out tasks consistent with the requirements of the job, check for serviceability and rectify or report any faults Completed |
Evidence:
|
Identify environmental protection requirements from the project environmental management plan, and confirm and apply to the allotted task Completed |
Evidence:
|
Prepare for formwork erection
|
|
Identify location and design of formwork/falsework from site drawings, engineers' design and specifications Completed |
Evidence:
|
Accurately place key set out locations to requirements of job drawings Completed |
Evidence:
|
Prepare work area and materials for the erection of formwork/falsework Completed |
Evidence:
|
Assemble formwork shutters to design form requirements and specified dimensions Completed |
Evidence:
|
Sequentially erect formwork support system (falsework) according to initial set out and standards Completed |
Evidence:
|
Check scaffolding and/or hand railing where required in accordance with job specification and standards Completed |
Evidence:
|
Place bracing of formwork support to job requirements and design specifications to maintain rigidity and stability Completed |
Evidence:
|
Set support system to correct height level, line and tolerance Completed |
Evidence:
|
Erect formwork
|
|
Fabricate, position and fix formwork for beams, drop panels and cantilevers into place Completed |
Evidence:
|
Assemble, erect and fix formwork for walls into place, plumb and to specified tolerance Completed |
Evidence:
|
Fabricate, position and fix soffit formwork into place Completed |
Evidence:
|
Fix edge boxing to formwork in correct position and plumb to alignment. Completed |
Evidence:
|
Brace formwork Completed |
Evidence:
|
Install cast-ins, inserts and penetration blocks to locations Completed |
Evidence:
|
Inspect formwork
|
|
Inspect erected formwork and formwork support system for safety and quality of work in accordance with standards Completed |
Evidence:
|
Remove loose dirt, sawdust and other waste material with due care to welfare of site personnel and public Completed |
Evidence:
|
Apply release agent to formwork in accordance with specifications Completed |
Evidence:
|
Monitor formwork and support system during concrete pour Completed |
Evidence:
|
Stripping of formwork
|
|
Obtain approval to remove formwork support from appropriate site authority Completed |
Evidence:
|
Carefully remove edge boxing and braces, denail, clean and store/stack Completed |
Evidence:
|
Back off support system to appropriate height to loosen soffit decking Completed |
Evidence:
|
Safely and sequentially remove formwork, denail and relocate or store Completed |
Evidence:
|
Select and install appropriate back propping system, where applicable, according to standards and engineers' requirements Completed |
Evidence:
|
Clean up
|
|
Clear work area and dispose of or recycle materials in accordance with project environmental management plan Completed |
Evidence:
|
Clean, check, maintain and store plant, tools and equipment Completed |
Evidence:
|