Evidence Guide: RIISRM303B - Move and position materials to form stockpiles

Student: __________________________________________________

Signature: _________________________________________________

Tips for gathering evidence to demonstrate your skills

The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!

From the Wiki University

 

RIISRM303B - Move and position materials to form stockpiles

What evidence can you provide to prove your understanding of each of the following citeria?

Organise for stockpiling

  1. Access, interpret and apply compliance documentation relevant to moving and positioning of materials to form stockpiles
  2. Receive, interpret and clarify shift changeover details
  3. Communicate with other personnel using approved communication methods
  4. Select personal protective equipment appropriate for work activities
  5. Identify, address and report environmental issues
  6. Confirm stockpile boundaries and signage are erected according to site procedures
  7. Adhere to emergency procedures
  8. Identify, address and report potential risks and hazards
Access, interpret and apply compliance documentation relevant to moving and positioning of materials to form stockpiles

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Receive, interpret and clarify shift changeover details

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Communicate with other personnel using approved communication methods

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, address and report environmental issues

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Confirm stockpile boundaries and signage are erected according to site procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Adhere to emergency procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, address and report potential risks and hazards

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Stockpile materials

  1. Stockpile materials in specified location
  2. Inspect stockpile structure and surrounding area
  3. Identify and manage contaminants to protect quality of material and protect equipment and environment
  4. Construct stockpile according to site stockpile plan
  5. Ensure stockpile has adequate drainage to minimise contamination of stockpile and surrounding areas
  6. Maintain pad according to site parameters
  7. Complete all required documentation clearly, concisely and on time
  8. Pass on end of shift information to oncoming shift
Stockpile materials in specified location

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Inspect stockpile structure and surrounding area

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and manage contaminants to protect quality of material and protect equipment and environment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Construct stockpile according to site stockpile plan

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Ensure stockpile has adequate drainage to minimise contamination of stockpile and surrounding areas

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Maintain pad according to site parameters

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Complete all required documentation clearly, concisely and on time

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Pass on end of shift information to oncoming shift

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assessed

Teacher: ___________________________________ Date: _________

Signature: ________________________________________________

Comments:

 

 

 

 

 

 

 

 

Instructions to Assessors

Evidence Guide

The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.

Overview of assessment

Critical aspects for assessment and evidence required to demonstrate competency in this unit

The evidence required to demonstrate competency in this unit must be relevant to worksite operations and satisfy all of the requirements of the performance criteria, required skills and knowledge and the range statement of this unit and include evidence of the following:

knowledge of the requirements, procedures and instructions for moving and positioning of materials to form stockpiles

implementation of requirements, procedures and techniques for the safe, effective and efficient moving and positioning of materials to form stockpiles

working with others to move and position materials to form stockpiles that meets all of the required outcomes

consistent timely completion of moving and positioning of materials to form stockpiles that safely, effectively and efficiently meets the required outcomes

Context of and specific resources for assessment

This unit must be assessed in the context of the work environment. Where personal safety or environmental damage are limiting factors, assessment may occur in a simulated environment provided it is realistic and sufficiently rigorous to cover all aspects of workplace performance, including task skills, task management skills, contingency management skills and job role environment skills.

The assessment environment should not disadvantage the participant. For example, language, literacy and numeracy demands of assessment should not be greater than those required on the job.

Customisation of assessment and delivery environment to sensitively accommodate cultural diversity.

Aboriginal people and other people from a non English speaking background may have second language issues.

Assessment of this competency requires typical resources normally used in the work environment. Selection and use of resources for particular worksites may differ due to site circumstances.

Where applicable, physical resources should include equipment modified for people with disabilities.

Access must be provided to appropriate learning and/or assessment support when required.

Method of assessment

This unit may be assessed in a holistic way with other units of competency. The assessment strategy for this unit must verify required knowledge and skill and practical application using more than one of the following assessment methods:

written and/or oral assessment of the candidate's required knowledge

observed, documented and/or first hand testimonial evidence of the candidate's:

implementation of appropriate requirement, procedures and techniques for the safe, effective and efficient achievement of required outcomes

consistently achieving the required outcomes

first hand testimonial evidence of the candidate's:

working with others to move and position materials to form stockpiles

Guidance information for assessment

Consult the SkillsDMC User Guide for further information on assessment including access and equity issues.

Required Skills and Knowledge

Required skills

Specific skills are required to achieve the performance criteria in this unit, particularly for the application in the various circumstances in which this unit may be applied. This includes the ability to carry out the following as required to move and position materials to form stockpiles:

apply legislative, organisation and site requirements and procedures

apply materials dumping techniques

apply procedures for operating, maintaining and cleaning equipment

apply hazard identification procedures

interpret plans, maps, specifications

apply procedures for monitoring operations

apply OHS procedures

apply defect reporting requirements

use hand and power tools

apply stockpile safety requirements

Required knowledge

Specific knowledge is required to achieve the performance criteria of this unit, particularly its application in a variety of circumstances in which the unit may be used. This includes knowledge of the following as required to move and position materials to form stockpiles:

bund construction and maintenance procedures

drainage principles

emergency procedures

environmental principles

isolation principles

metallurgical and technical data

selection of equipment

operational procedures and checks

road rules

signage

stockpile safety requirements

stockpiling characteristics and limitations

stockpiling procedures

types of ores

wet and dry working procedures

Range Statement

The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.

Relevant compliance documentation may include:

legislative, organisation and site requirements and procedures

manufacturer's guidelines and specifications

Australian standards

code of practice

Employment and Workplace Relations legislation

Equal Employment Opportunity and Disability Discrimination legislation

A stockpile may be temporary or permanent and may be:

a hole

bulk storage

formation of earthworks (cone, flat)

silo

warehouse

Environmental issues may include:

drainage

dust and fumes

emissions

hazardous chemicals

noise

run-off

spills

waste management and disposal

water quality

Boundaries may be fixed or mobile and may include:

chalk and paint markings

cones

flag and string fences

wire

Signage may include:

danger

height

one way

safety

stop

stockpile numbering or name

Hazards may include:

day and night

degree of compaction

dry and wet

location of water table

mobile equipment in area

overhead power-lines

persons on foot

slope of working surface

stable ground and broken ground

working at heights

working over old underground workings and voids

Materials may be wet or dry and may include:

beneficiation product

crushed ore

road base

run of mine ore

sand

gravel

crushed aggregate

tailings

topsoil

waste rock

Inspections may include:

detection of contaminants and hazards

isolations

ore types

overhead clearance (e.g. height limitations or power links for cranes or trucks)

personal proximity

possible faults and problems

safety equipment

Contaminants are anything other than the ore or products and may include:

containers

packaging

fuels

metal

oils

piping

rubbish

timber

Equipment may include:

bins

conveyors

dust suppression equipment

mobile equipment

Stockpile plan may include:

map

coordination of activities

total area

segregation of material types

signage requirements

stockpile construction details (angle of repose, height)

compaction requirements (coal mining)