NTISthis.com

Evidence Guide: RIIWBP202A - Distribute tailings

Student: __________________________________________________

Signature: _________________________________________________

Tips for gathering evidence to demonstrate your skills

The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!

From the Wiki University

 

RIIWBP202A - Distribute tailings

What evidence can you provide to prove your understanding of each of the following citeria?

Plan and prepare

  1. Access, interpret and apply compliance documentation relevant to distribution of tailings
  2. Receive, interpret and clarify shift changeover details
  3. Communicate with other personnel using approved communication methods
  4. Select personal protective equipment appropriate for work activities
  5. Select appropriate type of auxiliary equipment for work activities
  6. Perform equipment pre-start checks
  7. Identify, address and report potential risks and hazards
  8. Identify, address and report environmental issues
  9. Adhere to emergency procedures
  10. Use approved dust suppression and extraction methods
  11. Prepare site for positioning of equipment
  12. Position and stabilise equipment according to work plan
Access, interpret and apply compliance documentation relevant to distribution of tailings

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Receive, interpret and clarify shift changeover details

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Communicate with other personnel using approved communication methods

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select appropriate type of auxiliary equipment for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Perform equipment pre-start checks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, address and report potential risks and hazards

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, address and report environmental issues

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Adhere to emergency procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Use approved dust suppression and extraction methods

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Prepare site for positioning of equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Position and stabilise equipment according to work plan

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Start-up equipment in sequence

  1. Carry out start-up procedures and complete start-up checks according to plant configurations and system requirements
  2. Confirm plant is operational
Carry out start-up procedures and complete start-up checks according to plant configurations and system requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Confirm plant is operational

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Monitor and disperse tailings

  1. Read and interpret data from equipment indicators to determine deposition parameters
  2. Continuously inspect plant and identify defects and potential problems
  3. Adjust equipment to approved operating parameters to optimise performance, maintain efficiency and to meet tailings quality targets
  4. Control feed to equipment
  5. Monitor bunded areas and manage overflows
  6. Complete all required documentation
  7. Identify, address and report hazards
  8. Report spillages to meet environmental guidelines
  9. Pass on end of shift information to oncoming shift
  10. Ensure tailings meet fill plant operating parameters
Read and interpret data from equipment indicators to determine deposition parameters

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Continuously inspect plant and identify defects and potential problems

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Adjust equipment to approved operating parameters to optimise performance, maintain efficiency and to meet tailings quality targets

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Control feed to equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Monitor bunded areas and manage overflows

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Complete all required documentation

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, address and report hazards

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Report spillages to meet environmental guidelines

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Pass on end of shift information to oncoming shift

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Ensure tailings meet fill plant operating parameters

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Conduct housekeeping activities

  1. Clean equipment to maintain condition of equipment and ensure safe and efficient operations
  2. Clean and store auxiliary service equipment
Clean equipment to maintain condition of equipment and ensure safe and efficient operations

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean and store auxiliary service equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Shutdown in sequence and/or isolate equipment

  1. Flush lines to remove all material
  2. Shutdown or isolate equipment based on process and safety requirements
  3. Perform post shutdown or isolation checks
Flush lines to remove all material

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Shutdown or isolate equipment based on process and safety requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Perform post shutdown or isolation checks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assessed

Teacher: ___________________________________ Date: _________

Signature: ________________________________________________

Comments:

 

 

 

 

 

 

 

 

Instructions to Assessors

Evidence Guide

The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.

Overview of assessment

Critical aspects for assessment and evidence required to demonstrate competency in this unit

The evidence required to demonstrate competency in this unit must be relevant to worksite operations and satisfy all of the requirements of the performance criteria, required skills and knowledge and the range statement of this unit and include evidence of the following:

knowledge of the requirements, procedures and instructions for the distribution of tailings

implementation of requirements, procedures and techniques for the safe, effective and efficient completion of the distribution of tailings

working with others to undertake and complete the distribution of tailings that meets all of the required outcomes

consistent timely completion of the distribution of tailings that safely, effectively and efficiently meets the required outcomes

Context of and specific resources for assessment

This unit must be assessed in the context of the work environment. Where personal safety or environmental damage are limiting factors, assessment may occur in a simulated environment provided it is realistic and sufficiently rigorous to cover all aspects of workplace performance, including task skills, task management skills, contingency management skills and job role environment skills.

The assessment environment should not disadvantage the participant. For example, language, literacy and numeracy demands of assessment should not be greater than those required on the job.

Customisation of assessment and delivery environment to sensitively accommodate cultural diversity.

Aboriginal people and other people from a non English speaking background may have second language issues.

Assessment of this competency requires typical resources normally used in the work environment. Selection and use of resources for particular worksites may differ due to site circumstances.

Where applicable, physical resources should include equipment modified for people with disabilities.

Access must be provided to appropriate learning and/or assessment support when required.

Method of assessment

This unit may be assessed in a holistic way with other units of competency. The assessment strategy for this unit must verify required knowledge and skill and practical application using more than one of the following assessment methods:

written and/or oral assessment of the candidate's required knowledge

observed, documented and/or first hand testimonial evidence of the candidate's:

implementation of appropriate requirement, procedures and techniques for the safe, effective and efficient achievement of required outcomes

consistently achieving the required outcomes

first hand testimonial evidence of the candidate's:

working with others to undertake and complete the distribution of tailings

Guidance information for assessment

Consult the SkillsDMC User Guide for further information on assessment including access and equity issues.

Required Skills and Knowledge

Required skills

Specific skills are required to achieve the performance criteria in this unit, particularly for the application in the various circumstances in which this unit may be applied. This includes the ability to carry out the following as required to distribute tailings:

apply legislative, organisation and site requirements and procedures

maintain, clean and operate, equipment

apply hazard identification procedures

apply hazardous goods handling requirements and procedures

interpret reports

apply lifting techniques (manual, cranes and loads)

apply records maintenance requirements

apply safe work practices

use hand and power tools

Required knowledge

Specific knowledge is required to achieve the Performance Criteria of this unit, particularly its application in a variety of circumstances in which the unit may be used. This includes knowledge of the following, as required to distribute tailings:

breakdown procedures

emergency procedures

environmental procedures

equipment processes, technical capability and limitations

equipment safety requirements

flushing lines

hazard identification and management

identifying repair requirements

isolation procedures

metallurgical and technical data (basic)

occupational health and safety procedures

operational procedures and checks

pumping system

reclaim ponds/dams

safety requirements

securing pipes

security procedures (e.g. shutting of gates)

site procedures

spillage procedures

tailings

wet and dry working procedures

Range Statement

The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.

Relevant compliance documentation

may include:

legislative, organisation and site requirements and procedures

manufacturer's guidelines and specifications

Australian standards

code of practice

Employment and Workplace Relations legislation

Equal Employment Opportunity and Disability Discrimination legislation

Auxiliary equipment may be anything that is portable and mobile that is not part of the fixed infrastructure: These may include:

compressors

cyclones

hand and power tools

hoses (water and air)

lines and ropes

loaders, pontoons, boats

thickening agents (e.g. de-scaling)

Pre-start checks may include:

availability of equipment

detection of conditions that are unusual

drive through plant

personnel availability

Environmental issues may include:

drainage

dust

emissions

flora and fauna

hazardous chemicals

recycling (e.g. water)

run-off/spills

waste management and disposal

water quality

Start-up procedures may include:

checking interlocks

checks distribution control system (DCS)

chutes

drive belts

isolations

material transfer system condition (e.g. leaks, blockages)

pumping system

remote systems (e.g. telemetry)

valves

Plant may include:

decant towers and ponds

pumps and siphons

spigots

tailings pipeline

valves

Indicator readings may measure:

concentration (e.g. cyanide)

current

density

flow

levels

pressure

speed (e.g. pump)

unusual noises

Monitoring may include the checking of:

blockages

current draw

detecting noises and smells

flow rates

missing components (e.g. spigots)

overloads

pressures

spillages

wear and tear

Overflow areas may include:

collection dams

scour pits

Cleaning methods may include:

hosing with water

Materials may include:

reagents

slurry

tailings

water

Post-shutdown checks are:

beaching

density

location of discharge points

regulate decant water removal

relocation of spigots