NTISthis.com

Evidence Guide: TLILIC0008 - Licence to operate a non-slewing mobile crane (greater than 3 tonnes capacity)

Student: __________________________________________________

Signature: _________________________________________________

Tips for gathering evidence to demonstrate your skills

The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!

From the Wiki University

 

TLILIC0008 - Licence to operate a non-slewing mobile crane (greater than 3 tonnes capacity)

What evidence can you provide to prove your understanding of each of the following citeria?

Plan work/task

  1. Task requirements are identified from work orders or equivalent and a lift plan is confirmed with associated personnel and a site inspection is conducted in accordance with workplace procedures
  2. Work area operating surface is confirmed to determine the quality of ground suitability for operational use of non-slewing mobile crane in accordance with workplace procedures
  3. Non-slewing mobile crane rated capacity (RC) and the lifting gear Working Load Limit (WLL)are established for the load/s and work/task requirements in accordance with manufacturer requirements and workplace procedures
  4. Appropriate paths for operating the mobile crane and moving and placing load/s in work area are assessed and determined in accordance with workplace procedures
  5. Relevant hazard identification and risk elimination/control measures are applied and advised to associated personnel in accordance with workplace procedures
  6. Traffic management plan implementation is confirmed and followed in accordance with workplace procedures
  7. Appropriate communication procedures are identified and tested with associated personnel in accordance with workplace procedures
  8. All tasks are confirmed to ensure requirements for the relevant work area in accordance with a lift plan and workplace procedures
Task requirements are identified from work orders or equivalent and a lift plan is confirmed with associated personnel and a site inspection is conducted in accordance with workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Work area operating surface is confirmed to determine the quality of ground suitability for operational use of non-slewing mobile crane in accordance with workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Non-slewing mobile crane rated capacity (RC) and the lifting gear Working Load Limit (WLL)are established for the load/s and work/task requirements in accordance with manufacturer requirements and workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Appropriate paths for operating the mobile crane and moving and placing load/s in work area are assessed and determined in accordance with workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Relevant hazard identification and risk elimination/control measures are applied and advised to associated personnel in accordance with workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Traffic management plan implementation is confirmed and followed in accordance with workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Appropriate communication procedures are identified and tested with associated personnel in accordance with workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

All tasks are confirmed to ensure requirements for the relevant work area in accordance with a lift plan and workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Prepare for work/task

  1. Consultation with workplace personnel is established and maintained to ensure lift plan is clear and consistent with site requirements in accordance with a lift plan and workplace procedures
  2. Risk control measures for hazards identified are checked for implementation in accordance with the lift plan and safe work procedures
  3. Non-slewing mobile crane is accessed safely in accordance with manufacturer requirements and safe work procedures
  4. Pre-start crane checks are carried out and any damage and defects are reported, recorded and appropriate action is taken in accordance with manufacturer requirements and safe work procedures
  5. Mobile crane is set up correctly with any lifting gear as per the lift plan in accordance with relevant manufacturer requirements including load chart/s and safe work procedures
  6. Fly jib (if fitted) is set up as required in accordance with specific manufacturer requirements and safe work procedures
  7. Operational checks are carried out and any damage and defects are reported, recorded and appropriate action is taken in accordance with manufacturer requirements and safe work procedures
  8. Crane logbook is checked to confirm current compliance, is correct for the crane type, is completed and signed and required rectifications have been signed off in accordance with manufacturer requirements and safe work procedures
  9. Weather and work environment conditions are assessed to determine any impact on mobile crane operations in accordance with manufacturer requirements and safe work procedures
Consultation with workplace personnel is established and maintained to ensure lift plan is clear and consistent with site requirements in accordance with a lift plan and workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Risk control measures for hazards identified are checked for implementation in accordance with the lift plan and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Non-slewing mobile crane is accessed safely in accordance with manufacturer requirements and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Pre-start crane checks are carried out and any damage and defects are reported, recorded and appropriate action is taken in accordance with manufacturer requirements and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Mobile crane is set up correctly with any lifting gear as per the lift plan in accordance with relevant manufacturer requirements including load chart/s and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Fly jib (if fitted) is set up as required in accordance with specific manufacturer requirements and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Operational checks are carried out and any damage and defects are reported, recorded and appropriate action is taken in accordance with manufacturer requirements and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Crane logbook is checked to confirm current compliance, is correct for the crane type, is completed and signed and required rectifications have been signed off in accordance with manufacturer requirements and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Weather and work environment conditions are assessed to determine any impact on mobile crane operations in accordance with manufacturer requirements and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Perform work/task

  1. Lifts are determined within the RC of the non slewing mobile crane in accordance with the load chart/s and lift plan
  2. Boom/jib and hook block is safely positioned over the load following directions from associated personnel in accordance with the lift plan and safe work procedures
  3. Lifting gear where required is connected to the load and used safely in accordance with the lift plan, safe work procedures and manufacturer requirements
  4. Test lift is carried out in accordance with dogging and safe work procedures
  5. Loads are transferred using relevant crane movements and tag lines as required, in accordance with lift plan and safe work procedures
  6. Load and crane movement is monitored constantly and crane is operated safely in accordance with lift plan and safe work procedures
  7. All required communication signals are correctly interpreted and followed whilst crane is operated in accordance with the lift plan and safe work procedures
  8. Load is lowered and landed safely in accordance with lift plan and safe work procedures
  9. Lifting gear is disconnected from load and crane is positioned safely and efficiently for next task in accordance with lift plan and safe work procedures
  10. Crane boom/jib, lifting gear and associated equipment is stowed and secured as required in accordance with manufacturer requirements and safe work procedures
  11. Relevant motion locks and brakes are applied as required in accordance with manufacturer requirements and safe work procedures
  12. Crane is shut down and secured to prevent unauthorised access/use in accordance with safe work procedures
  13. Post-operational crane checks are carried out in accordance with legislative responsibilities, safe work procedures and manufacturer requirements
  14. Task requirements are identified from work orders or equivalent and a lift plan is confirmed with associated personnel and a site inspection is conducted in accordance with workplace procedures
Lifts are determined within the RC of the non slewing mobile crane in accordance with the load chart/s and lift plan

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Boom/jib and hook block is safely positioned over the load following directions from associated personnel in accordance with the lift plan and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Lifting gear where required is connected to the load and used safely in accordance with the lift plan, safe work procedures and manufacturer requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Test lift is carried out in accordance with dogging and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Loads are transferred using relevant crane movements and tag lines as required, in accordance with lift plan and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Load and crane movement is monitored constantly and crane is operated safely in accordance with lift plan and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

All required communication signals are correctly interpreted and followed whilst crane is operated in accordance with the lift plan and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Load is lowered and landed safely in accordance with lift plan and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Lifting gear is disconnected from load and crane is positioned safely and efficiently for next task in accordance with lift plan and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Crane boom/jib, lifting gear and associated equipment is stowed and secured as required in accordance with manufacturer requirements and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Relevant motion locks and brakes are applied as required in accordance with manufacturer requirements and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Crane is shut down and secured to prevent unauthorised access/use in accordance with safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Post-operational crane checks are carried out in accordance with legislative responsibilities, safe work procedures and manufacturer requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Task requirements are identified from work orders or equivalent and a lift plan is confirmed with associated personnel and a site inspection is conducted in accordance with workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Work area operating surface is confirmed to determine the quality of ground suitability for operational use of non-slewing mobile crane in accordance with workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Non-slewing mobile crane rated capacity (RC) and the lifting gear Working Load Limit (WLL)are established for the load/s and work/task requirements in accordance with manufacturer requirements and workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Appropriate paths for operating the mobile crane and moving and placing load/s in work area are assessed and determined in accordance with workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Relevant hazard identification and risk elimination/control measures are applied and advised to associated personnel in accordance with workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Traffic management plan implementation is confirmed and followed in accordance with workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Appropriate communication procedures are identified and tested with associated personnel in accordance with workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

All tasks are confirmed to ensure requirements for the relevant work area in accordance with a lift plan and workplace procedures

  1. Consultation with workplace personnel is established and maintained to ensure lift plan is clear and consistent with site requirements in accordance with a lift plan and workplace procedures
Consultation with workplace personnel is established and maintained to ensure lift plan is clear and consistent with site requirements in accordance with a lift plan and workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Risk control measures for hazards identified are checked for implementation in accordance with the lift plan and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Non-slewing mobile crane is accessed safely in accordance with manufacturer requirements and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Pre-start crane checks are carried out and any damage and defects are reported, recorded and appropriate action is taken in accordance with manufacturer requirements and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Mobile crane is set up correctly with any lifting gear as per the lift plan in accordance with relevant manufacturer requirements including load chart/s and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Fly jib (if fitted) is set up as required in accordance with specific manufacturer requirements and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Operational checks are carried out and any damage and defects are reported, recorded and appropriate action is taken in accordance with manufacturer requirements and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Crane logbook is checked to confirm current compliance, is correct for the crane type, is completed and signed and required rectifications have been signed off in accordance with manufacturer requirements and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Weather and work environment conditions are assessed to determine any impact on mobile crane operations in accordance with manufacturer requirements and safe work procedures

  1. Lifts are determined within the RC of the non slewing mobile crane in accordance with the load chart/s and lift plan
Lifts are determined within the RC of the non slewing mobile crane in accordance with the load chart/s and lift plan

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Boom/jib and hook block is safely positioned over the load following directions from associated personnel in accordance with the lift plan and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Lifting gear where required is connected to the load and used safely in accordance with the lift plan, safe work procedures and manufacturer requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Test lift is carried out in accordance with dogging and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Loads are transferred using relevant crane movements and tag lines as required, in accordance with lift plan and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Load and crane movement is monitored constantly and crane is operated safely in accordance with lift plan and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

All required communication signals are correctly interpreted and followed whilst crane is operated in accordance with the lift plan and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Load is lowered and landed safely in accordance with lift plan and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Lifting gear is disconnected from load and crane is positioned safely and efficiently for next task in accordance with lift plan and safe work procedures

  1. Crane boom/jib, lifting gear and associated equipment is stowed and secured as required in accordance with manufacturer requirements and safe work procedures
Crane boom/jib, lifting gear and associated equipment is stowed and secured as required in accordance with manufacturer requirements and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Relevant motion locks and brakes are applied as required in accordance with manufacturer requirements and safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Crane is shut down and secured to prevent unauthorised access/use in accordance with safe work procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Post-operational crane checks are carried out in accordance with legislative responsibilities, safe work procedures and manufacturer requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assessed

Teacher: ___________________________________ Date: _________

Signature: ________________________________________________

Comments:

 

 

 

 

 

 

 

 

Instructions to Assessors

Required Skills and Knowledge
Range Statement

Range is restricted to essential operating conditions and any other variables essential to the work environment.

Non -essential conditions may be found in the Companion Volume Implementation Guide.