The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Plan and prepare work
|
|
Safety issues are identified in accordance with Work, Health and Safety (WHS)/Occupational Health and Safety (OHS) regulations, industry standards and workplace procedures Completed |
Evidence:
|
Work, hydro generator synchronous condenser plant and type of start requirements are identified from appropriate personnel and documentation, in accordance with workplace procedures Completed |
Evidence:
|
Turbine running up and loading schedule are ascertained from relevant documentation, in accordance with workplace procedures Completed |
Evidence:
|
Hydro generator synchronous condenser plant inspection, preoperational tests and field preparation for service are carried out, in accordance with manufacturers' recommendations and workplace procedures Completed |
Evidence:
|
Hydro generator synchronous condenser plant operational prerequisites are established, in accordance with manufacturers' recommendations and workplace procedures Completed |
Evidence:
|
Sequence for recommissioning of hydro generator synchronous condenser plant is determined, in accordance with workplace procedures Completed |
Evidence:
|
Work, hydro generator synchronous condenser plant and type of start requirements are identified from appropriate personnel and documentation, in accordance with workplace procedures |
|
Completed |
Evidence:
|
Turbine running up and loading schedule are ascertained from relevant documentation, in accordance with workplace procedures |
|
Completed |
Evidence:
|
Hydro generator synchronous condenser plant inspection, preoperational tests and field preparation for service are carried out, in accordance with manufacturers' recommendations and workplace procedures |
|
Completed |
Evidence:
|
Hydro generator synchronous condenser plant operational prerequisites are established, in accordance with manufacturers' recommendations and workplace procedures |
|
Completed |
Evidence:
|
Sequence for recommissioning of hydro generator synchronous condenser plant is determined, in accordance with workplace procedures |
|
Completed |
Evidence:
|
Operate hydro generator synchronous condenserplant
|
|
Hydro generator synchronous condenser plant is operated, in accordance with workplace procedures and manufacturers' recommendations Completed |
Evidence:
|
Hydro generator synchronous condenser plant is monitored, in accordance with workplace procedures, to detect deviations from normal operating conditions |
|
Completed |
Evidence:
|
Corrective actions are taken to rectify abnormalities, in accordance with manufacturers' recommendations and workplace procedures |
|
Completed |
Evidence:
|
Test hydro generator synchronous condenserplant operation
|
|
Tests are performed on hydro generator synchronous condenser plant, in accordance with workplace procedures Completed |
Evidence:
|
Corrective action is taken when response does not meet with documentation, hydro generator synchronous condenser plant integrity or personnel safety requirements |
|
Completed |
Evidence:
|
Hydro generator synchronous condenser plant is returned to required operational status upon completion of testing, in accordance with workplace procedures |
|
Completed |
Evidence:
|
Analysehydro generator plant faults
|
|
Cause of abnormal hydro generator synchronous condenser plant operating conditions are identified by analysing technical and operational information, in accordance with workplace procedures Completed |
Evidence:
|
Hydro generator synchronous condenser plant integrity and personnel safety is maintained, in accordance with workplace procedures, through consultation with appropriate personnel and technical and operational documentation |
|
Completed |
Evidence:
|
Appropriate personnel are notified when defects are detected, in accordance with workplace procedures |
|
Completed |
Evidence:
|
Complete documentation
|
|
Plant problems, movements and status are reported, in accordance with workplace procedures Completed |
Evidence:
|
Documentation is updated, in accordance with workplace procedures |
|
Completed |
Evidence:
|