The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Plan and prepare work
|
|
Safety issues related to operating and monitoring generator and/or alternator auxiliary plant are identified, in accordance with workplace procedures and Work, Health and Safety (WHS)/Occupational Health and Safety(OHS) regulations and legislative requirements Completed |
Evidence:
|
Work requirements and generator and/or alternator auxiliary plant are identified from appropriate personnel and documentation, in accordance with workplace procedures Completed |
Evidence:
|
Generator and/or alternator auxiliary running up and loading schedule is ascertained from relevant documentation, in accordance with workplace procedures and site requirements Completed |
Evidence:
|
Inspection, preoperational tests and field preparations for generator and/or alternator auxiliary plant service are carried out, in accordance with workplace procedures and manufacturers' recommendations Completed |
Evidence:
|
Generator and/or alternator auxiliary plant operational prerequisites are established, in accordance with workplace procedures and manufacturers' recommendations Completed |
Evidence:
|
Sequence for recommissioning of generator and/or alternator auxiliary plant is determined, in accordance with workplace procedures and site requirements Completed |
Evidence:
|
Work requirements and generator and/or alternator auxiliary plant are identified from appropriate personnel and documentation, in accordance with workplace procedures |
|
Completed |
Evidence:
|
Generator and/or alternator auxiliary running up and loading schedule is ascertained from relevant documentation, in accordance with workplace procedures and site requirements |
|
Completed |
Evidence:
|
Inspection, preoperational tests and field preparations for generator and/or alternator auxiliary plant service are carried out, in accordance with workplace procedures and manufacturers' recommendations |
|
Completed |
Evidence:
|
Generator and/or alternator auxiliary plant operational prerequisites are established, in accordance with workplace procedures and manufacturers' recommendations |
|
Completed |
Evidence:
|
Sequence for recommissioning of generator and/or alternator auxiliary plant is determined, in accordance with workplace procedures and site requirements |
|
Completed |
Evidence:
|
Operate generator/alternator auxiliaryplant
|
|
Generator and/or alternator auxiliary plant is operated within limits of its' design and regulators requirements, in accordance with workplace procedures Completed |
Evidence:
|
Generator and/or alternator auxiliary plant is monitored and observed, in accordance with workplace procedures, to detect deviations from required operating conditions |
|
Completed |
Evidence:
|
Corrective actions are taken to rectify generator and/or alternator auxiliary plant abnormalities, in accordance with workplace procedures and manufacturers' recommendations |
|
Completed |
Evidence:
|
Test generator/alternator auxiliaryplant operation
|
|
Operational tests are performed, in accordance with workplace procedures Completed |
Evidence:
|
Generator and/or alternator auxiliary plant is observed for correct operational response, in accordance with workplace procedures |
|
Completed |
Evidence:
|
Corrective action is taken, in accordance with workplace procedures, when response does not meet with documentation, generator or alternator auxiliary plant integrity or personnel safety requirements |
|
Completed |
Evidence:
|
Generator and/or alternator auxiliary plant is returned to required operational status upon completion of testing, in accordance with workplace procedures |
|
Completed |
Evidence:
|
Analyse generator/alternator auxiliaryplant faults
|
|
Cause of abnormal generator and/or alternator auxiliary plant operating conditions are identified, in accordance with workplace procedures, by analysing technical and operational information Completed |
Evidence:
|
Corrective actions to rectify generator and/or alternator auxiliary plant faults are determined, in accordance with workplace procedures |
|
Completed |
Evidence:
|
Generator and/or alternator auxiliary plant integrity and personnel safety is maintained, in accordance with workplace procedures, and in consultation with appropriate personnel and technical and operational documentation |
|
Completed |
Evidence:
|
Monitor and inspect generator/alternator auxiliaryplant
|
|
Generator and/or alternator auxiliary plant to be monitored and inspected is physically identified, in accordance with workplace procedures Completed |
Evidence:
|
Generator and/or alternator auxiliary plant is monitored and inspected, in accordance with workplace procedures, for normal operation or to detect deviations |
|
Completed |
Evidence:
|
Corrective action is taken, in accordance with workplace procedures |
|
Completed |
Evidence:
|
Appropriate personnel are notified, in accordance with workplace procedures, when defects are detected |
|
Completed |
Evidence:
|
Complete documentation
|
|
Generator and/or alternator auxiliary plant problems, movements, and status are reported, in accordance with workplace procedures Completed |
Evidence:
|
Documentation is updated, in accordance with workplace procedures |
|
Completed |
Evidence:
|