The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Monitor system/plant
|
|
Generator and excitation system and combined cycle plant to be monitored is physically identified, in accordance with workplace procedures Completed |
Evidence:
|
Generator and excitation system and combined cycle plant is monitored for normal operation to detect deviations, in accordance with workplace procedures Completed |
Evidence:
|
Corrective action is taken, in accordance with workplace procedures Completed |
Evidence:
|
Appropriate personnel are notified, in accordance with workplace procedures, when defects and abnormal operating conditions are detected Completed |
Evidence:
|
Plan for plant operation
|
|
Safety issues, including Work, Health and Safety (WHS)/Occupational Health and Safety (OHS) regulations, are identified, in accordance with workplace procedures and site requirements Completed |
Evidence:
|
Work, combined cycle plant and resource requirements are identified from relevant information and documentation, in accordance with workplace procedures |
|
Completed |
Evidence:
|
Preoperational checks are carried out on combined cycle plant, in accordance with workplace procedures and site requirements |
|
Completed |
Evidence:
|
Operate heat recovery steam generator
|
|
Gas turbine exhaust, gas flow and power output are adjusted to achieve required steam flow and conditions, in accordance with workplace procedures and operating requirements Completed |
Evidence:
|
Supplementary firing system is placed into and out of service, as required, in accordance with workplace procedures, to maintain steam flow and steam conditions |
|
Completed |
Evidence:
|
Combined cycle plant is operated within limits of its design, in accordance with workplace procedures and site requirements |
|
Completed |
Evidence:
|
Combined cycle plant is operated, monitored and observed, in accordance with workplace procedures, to detect deviations from required operating conditions |
|
Completed |
Evidence:
|
Corrective action is taken to rectify abnormalities in combined cycle plant, in accordance with manufacturers' specifications and workplace procedures |
|
Completed |
Evidence:
|
Operate generator and excitation system
|
|
Generator and excitation system is operated, in accordance with workplace procedures and manufacturer’s operating recommendations Completed |
Evidence:
|
Synchronising requirements are assessed, evaluated and implemented, in accordance with workplace procedures, to ensure generator and excitation system stability |
|
Completed |
Evidence:
|
Generator and excitation system is monitored and observed, in accordance with workplace procedures, to detect deviations from normal operating conditions |
|
Completed |
Evidence:
|
Corrective actions are taken to rectify generator and excitation system abnormalities, in accordance with workplace procedures and manufacturers' recommendations |
|
Completed |
Evidence:
|
Control generation of electrical energy
|
|
Generator output is adjusted to meet demand, in accordance with workplace procedures, whilst observing operating requirements Completed |
Evidence:
|
Reactive power generation and voltage regulation requirements are assessed, in accordance with workplace procedures, to ensure the generator and excitation system is controlled to achieve desired output |
|
Completed |
Evidence:
|
Generator stabilities and operating limits are assessed and the generator and excitation system is controlled to maintain those limits, in accordance with workplace procedures and manufacturers' recommendations |
|
Completed |
Evidence:
|
Generator cooling systems and limits are monitored and assessed, and excitation system is controlled to maintain those limits, in accordance with workplace procedures and manufacturers' recommendation |
|
Completed |
Evidence:
|
Coordinate generator and excitation systemoperations
|
|
Generator and excitation systems are operated, in accordance with workplace procedures, to meet workplace requirements whilst observing power generating plant limitations Completed |
Evidence:
|
Generator and excitation systems are monitored and observed, in accordance with workplace procedures, to detect deviations from normal operating conditions |
|
Completed |
Evidence:
|
Causes of abnormal generator and excitation system operating conditions are identified by analysing technical and operational data and information, in accordance with workplace procedures |
|
Completed |
Evidence:
|
Corrective action is taken to rectify generator and excitation system abnormalities, in accordance with workplace procedures and site requirements |
|
Completed |
Evidence:
|
Generator and excitation system integrity, personnel safety and continuity of supply are maintained, in accordance with workplace procedures |
|
Completed |
Evidence:
|
Consultation with appropriate personnel is undertaken, in accordance with workplace procedures and site requirements |
|
Completed |
Evidence:
|
Generator and excitation system is operated at optimum efficiency, in accordance with workplace procedures
|
|
Generator and excitation system and combined cycle plant to be monitored is physically identified, in accordance with workplace procedures Completed |
Evidence:
|
Generator and excitation system and combined cycle plant is monitored for normal operation to detect deviations, in accordance with workplace procedures |
|
Completed |
Evidence:
|
Corrective action is taken, in accordance with workplace procedures |
|
Completed |
Evidence:
|
Appropriate personnel are notified, in accordance with workplace procedures, when defects and abnormal operating conditions are detected |
|
Completed |
Evidence:
|
Test system/plant operation
|
|
Operational tests are performed, in accordance with workplace procedures Completed |
Evidence:
|
Generator and excitation system and combined cycle plant is observed for correct operational response, in accordance with workplace procedures |
|
Completed |
Evidence:
|
Corrective action is taken, in accordance with workplace procedures, when response does not meet documentation, combined cycle plant and generator and excitation system integrity or personnel safety requirements |
|
Completed |
Evidence:
|
Generator and excitation system and combined cycle plant is returned to required operational status, in accordance with workplace procedures, upon completion of testing |
|
Completed |
Evidence:
|
Analyse system/plant faults
|
|
Causes of abnormal generator and excitation system operating conditions are identified, in accordance with workplace procedures, by analysing technical and operational information Completed |
Evidence:
|
Corrective actions to rectify faults are determined, in accordance with workplace procedures |
|
Completed |
Evidence:
|
Generator and excitation system and combined cycle plant integrity and personnel safety are maintained, in accordance with workplace procedures, and in consultation with appropriate personnel and technical and operational documentation |
|
Completed |
Evidence:
|
Appropriate personnel are organised, in accordance with workplace procedures for investigation of identified operational abnormalities |
|
Completed |
Evidence:
|
Complete documentation
|
|
Combined cycle plant problems, movements, and status are reported, in accordance with workplace procedures Completed |
Evidence:
|
Documentation is updated, in accordance with workplace procedures |
|
Completed |
Evidence:
|