NTISthis.com

Evidence Guide: UEPOPS444 - Start and run-up a hydro turbine

Student: __________________________________________________

Signature: _________________________________________________

Tips for gathering evidence to demonstrate your skills

The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!

From the Wiki University

 

UEPOPS444 - Start and run-up a hydro turbine

What evidence can you provide to prove your understanding of each of the following citeria?

Plan and prepare work

  1. Safety issues are identified, in accordance with workplace procedures, Work Health and Safety (WHS)/Occupational Health and Safety (OHS) regulations and legislative requirements
  2. Work requirements are identified from relevant personnel and documentation, in accordance with workplace procedures
  3. Preoperational checks are carried out on hydro turbine plant, in accordance with manufacturers' recommendations, workplace procedures and site requirements
  4. Turbine running up and loading schedule are ascertained from relevant documentation, in accordance with workplace procedures
Safety issues are identified, in accordance with workplace procedures, Work Health and Safety (WHS)/Occupational Health and Safety (OHS) regulations and legislative requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Work requirements are identified from relevant personnel and documentation, in accordance with workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Preoperational checks are carried out on hydro turbine plant, in accordance with manufacturers' recommendations, workplace procedures and site requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Turbine running up and loading schedule are ascertained from relevant documentation, in accordance with workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Run-up hydro turbine

  1. Hydro turbine and alternator auxiliary systems are started up and hydro turbine is run up, in accordance with manufacturers' specifications and workplace procedures
  2. Hydro turbine is monitored and observed to detect deviations from normal run up operating conditions
  3. Corrective actions are taken to rectify hydro turbine abnormalities, in accordance with manufacturers' recommendations and workplace procedures
  4. Alternator is synchronised and connected to electrical system, in accordance with workplace procedures and manufacturers' recommendations
  5. Alternator is loaded, in accordance with workplace procedures, manufacturers' recommendations and regulators requirements
Hydro turbine and alternator auxiliary systems are started up and hydro turbine is run up, in accordance with manufacturers' specifications and workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Hydro turbine is monitored and observed to detect deviations from normal run up operating conditions

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Corrective actions are taken to rectify hydro turbine abnormalities, in accordance with manufacturers' recommendations and workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Alternator is synchronised and connected to electrical system, in accordance with workplace procedures and manufacturers' recommendations

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Alternator is loaded, in accordance with workplace procedures, manufacturers' recommendations and regulators requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Work requirements are identified from relevant personnel and documentation, in accordance with workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Preoperational checks are carried out on hydro turbine plant, in accordance with manufacturers' recommendations, workplace procedures and site requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Turbine running up and loading schedule are ascertained from relevant documentation, in accordance with workplace procedures

  1. Hydro turbine and alternator auxiliary systems are started up and hydro turbine is run up, in accordance with manufacturers' specifications and workplace procedures
Hydro turbine and alternator auxiliary systems are started up and hydro turbine is run up, in accordance with manufacturers' specifications and workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Hydro turbine is monitored and observed to detect deviations from normal run up operating conditions

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Corrective actions are taken to rectify hydro turbine abnormalities, in accordance with manufacturers' recommendations and workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Alternator is synchronised and connected to electrical system, in accordance with workplace procedures and manufacturers' recommendations

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Alternator is loaded, in accordance with workplace procedures, manufacturers' recommendations and regulators requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Test hydro turbineplant operation

  1. Tests are performed, in accordance with workplace procedures
Tests are performed, in accordance with workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Power generation system and hydro turbine plant are observed for correct operational response, in accordance with workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Analyseand reportsystem faults

  1. Causes of abnormal hydro turbine plant operating conditions are identified, in accordance with workplace procedures by analysing technical and operational information
Causes of abnormal hydro turbine plant operating conditions are identified, in accordance with workplace procedures by analysing technical and operational information

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Corrective action is taken, in accordance with workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Complete documentation

  1. Hydro turbine plant problems, movements and status are reported, in accordance with workplace procedures
Hydro turbine plant problems, movements and status are reported, in accordance with workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Documentation is updated, in accordance with workplace procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assessed

Teacher: ___________________________________ Date: _________

Signature: ________________________________________________

Comments:

 

 

 

 

 

 

 

 

Instructions to Assessors

Required Skills and Knowledge
Range Statement

Range is restricted to essential operating conditions and any other variables essential to the work environment.

Non-essential conditions may be found in the Companion Volume Implementation Guide.