The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Prepare for the installation and maintenance of de-energised LV underground polymeric cables
|
|
Works schedule(s), including drawings, plans, requirements, established procedures, and material lists, are received, analysed and confirmed, if necessary, by site inspection Completed |
Evidence:
|
Relevant requirements and established procedures for the work are communicated to all personnel and identified for all work sites Completed |
Evidence:
|
OHS policies and procedures related to requirements and established procedures for the installation and maintenance of de-energised LV underground polymeric cables are obtained and confirmed for the purposes of the work to be performed and communicated Completed |
Evidence:
|
Work is prioritised and sequenced following consultation with others for completion within acceptable timeframes and in accordance with established procedures Completed |
Evidence:
|
Hazards are identified, OHS risks assessed and control measures are prioritised, implemented and monitored including emergency exits kept clear according to established procedures. Completed |
Evidence:
|
Relevant work permits are obtained to access and perform work according to requirements and/or established procedures Completed |
Evidence:
|
Resources including personnel, equipment, tools and personal protective equipment required for the job are obtained and confirmed in working order Completed |
Evidence:
|
Relevant personnel at work site are confirmed current in First Aid and other related work procedures according to requirements Completed |
Evidence:
|
Liaison and communication issues with other/authorised personnel, authorities, clients and land owners are resolved to carry out work where necessary Completed |
Evidence:
|
Site is prepared according to the work schedule and to minimise risk and damage to property, commerce, and individuals in accordance with established procedures Completed |
Evidence:
|
Personnel participating in the work, including plant operators and contractors, are fully briefed and respective responsibilities confirmed where applicable in accordance with established procedures Completed |
Evidence:
|
Road signs, barriers and warning devices are positioned in accordance with requirements Completed |
Evidence:
|
Carry out the installation and maintenance of de-energised LV underground polymeric cables
|
|
OHS and sustainable energy principles and practices to reduce the incidents of accidents and minimise waste are monitored and followed in accordance with requirements and/or established procedures Completed |
Evidence:
|
Lifting, climbing, working in confined spaces and working aloft, and use of power tools/equipment, techniques and practices are safely followed and, currency according to requirements confirmed Completed |
Evidence:
|
Systems and circuits are isolated as required, proved safe to work on in accordance with the requirements/permits and established procedures Completed |
Evidence:
|
Essential knowledge and associated skills are applied for the safe installation and maintenance of de-energised LV underground polymeric cables to ensure completion in an agreed timeframe and, to quality standards with a minimum of waste according to requirements Completed |
Evidence:
|
De-energised LV underground polymeric cables are installed according to the work schedule and requirements/established procedures Completed |
Evidence:
|
Maintenance, including repair and/or replacement of LV underground polymeric cables is carried out, in accordance with the work schedule and requirements/established procedures Completed |
Evidence:
|
Hazard warnings and safety signs are recognised and hazards and assessed OHS risks are reported to the immediate authorised persons for directions according to established procedures. Completed |
Evidence:
|
Unplanned events in the installation and maintenance of de-energised LV underground polymeric cables are undertaken within the scope of established procedures Completed |
Evidence:
|
Known solutions to a variety of problems are applied using acquired essential knowledge and associated skills Completed |
Evidence:
|
Ongoing checks of quality of the work are undertaken in accordance with instructions and established procedures Completed |
Evidence:
|
Complete the installation and maintenance of de-energised LV underground polymeric cables
|
|
Work undertaken is checked against works schedule for conformance with requirements and anomalies reported in accordance with established procedures Completed |
Evidence:
|
Accidents and/or injuries are reported in accordance with requirements/established procedures, where applicable Completed |
Evidence:
|
Work site is rehabilitated, cleaned up and made safe in accordance with established procedures Completed |
Evidence:
|
Tools, equipment and any surplus resources and materials are, where appropriate, cleaned, checked and returned to storage in accordance with established procedures Completed |
Evidence:
|
Relevant work permit(s) are signed off and LV underground polymeric cables are returned to service in accordance with requirements Completed |
Evidence:
|
Works completion records, reports, drawings and/or documentation and information are finalised and processed and appropriate personnel notified Completed |