The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Prepare to pre-tension string the transmission overhead conductors and cables
|
|
Work instructions are received and confirmed. Completed |
Evidence:
|
Relevant requirements and established procedures to be followed for the work to be preformed are discussed with all personnel to establish and confirm the work schedule. Completed |
Evidence:
|
OHS policies and procedures to be followed for the work to be performed are received and confirmed. Completed |
Evidence:
|
Suggestions to assist in meeting pre-tension stringing of transmission overhead conductors and cables outcomes are made to others involved in the work. Completed |
Evidence:
|
Hazards are identified, OHS risks assessed and emergency exits kept clear according to given instructions and established procedures. Completed |
Evidence:
|
Scope of responsibility under the relevant work permit are received and confirmed according to requirements and established procedures with relevant personnel. Completed |
Evidence:
|
Resources including, equipment, tools and personnel protective equipment required for the job are obtained and, in working order according to established procedures. Completed |
Evidence:
|
Relevant responsibility associated with First Aid, Tower/Pole Top Rescue and/or other related work safety procedures at the work site are confirmed in accordance with requirements and established procedures to ensure safety measures are followed in the instance of an incident. Completed |
Evidence:
|
Client issues are referred to appropriate personnel in accordance with industry/acceptable /community standards. Completed |
Evidence:
|
Site is prepared according to given instructions and the work schedule for a quality outcome and to minimise risk and damage to property, commerce, and individuals in accordance and established procedures. Completed |
Evidence:
|
Road signs, barriers and other warning devices are positioned in accordance with given instructions and requirements. Completed |
Evidence:
|
Carry out pre-tension stringing of transmission overhead conductors and cables
|
|
OHS and sustainable energy principles and practices to reduce the incidents of accidents and minimise waste are followed in accordance with given instructions, requirements and/or established procedures. Completed |
Evidence:
|
Lifting, climbing, working aloft, and use of power tools/equipment, techniques and practices are safely followed in accordance with given instructions and, according to requirements confirmed to eliminate the prospects of incidents. Completed |
Evidence:
|
Operational knowledge for the pre-tension stringing of transmission overhead conductors and cables to be applied to the work is confirmed to ensure completion in an agreed timeframe and, to quality standards with a minimum of waste according to requirements and established procedures. Completed |
Evidence:
|
Pre-tension stringing of transmission overhead conductors and cables is carried out in accordance with given instructions and established routines/procedures. Completed |
Evidence:
|
Hazard warnings and safety signs are recognised and hazards and assessed OHS risks are reported to the immediate authorised persons for directions according to established procedures. Completed |
Evidence:
|
Non-routine events are referred to the immediate authorised personnel for directions according to established procedures. Completed |
Evidence:
|
Problems associated with pre-tension stringing of transmission overhead conductors and cables are dealt with using acquired known solutions and skills related to routine procedures to ensure work instructions and established procedures are met. Completed |
Evidence:
|
Ongoing checks of quality of the work are undertaken in accordance with given instructions and established procedures. Completed |
Evidence:
|
Complete pre-tension stringing of transmission overhead conductors and cables
|
|
Work undertaken is checked against work schedule and anomalies reported to authorised personnel in accordance with established procedures. Completed |
Evidence:
|
Accidents and/or incidents are actioned and reported to authorised personnel in accordance with established procedures. Completed |
Evidence:
|
Work site is rehabilitated, cleaned up and made safe in accordance with given instructions and established procedures. Completed |
Evidence:
|
Tools, equipment and any surplus resources and materials are, where appropriate, cleaned, checked and returned to storage in accordance with established procedures. Completed |
Evidence:
|
Appropriate personnel are notified of work completion according to established procedures. Completed |
Evidence:
|
Works completion records, report forms/data sheets are completed accurately in accordance with given instructions and established procedures. Completed |
Evidence:
|