Commission and decommission split air conditioning systems

Formats and tools

Unit Description
Reconstruct the unit from the xml and display it as an HTML page.
Assessment Tool
an assessor resource that builds a framework for writing an assessment tool
Assessment Template
generate a spreadsheet for marking this unit in a classroom environment. Put student names in the top row and check them off as they demonstrate competenece for each of the unit's elements and performance criteria.
Assessment Matrix
a slightly different format than the assessment template. A spreadsheet with unit names, elements and performance criteria in separate columns. Put assessment names in column headings to track which performance criteria each one covers. Good for ensuring that you've covered every one of the performance criteria with your assessment instrument (all assessement tools together).
Wiki Markup
mark up the unit in a wiki markup codes, ready to copy and paste into a wiki page. The output will work in most wikis but is designed to work particularly well as a Wikiversity learning project.
Evidence Guide
create an evidence guide for workplace assessment and RPL applicants
Competency Mapping Template
Unit of Competency Mapping – Information for Teachers/Assessors – Information for Learners. A template for developing assessments for a unit, which will help you to create valid, fair and reliable assessments for the unit, ready to give to trainers and students
Observation Checklist
create an observation checklist for workplace assessment and RPL applicants. This is similar to the evidence guide above, but a little shorter and friendlier on your printer. You will also need to create a seperate Assessor Marking Guide for guidelines on gathering evidence and a list of key points for each activity observed using the unit's range statement, required skills and evidence required (see the unit's html page for details)

Self Assessment Survey
A form for students to assess thier current skill levels against each of the unit's performance criteria. Cut and paste into a web document or print and distribute in hard copy.
Moodle Outcomes
Create a csv file of the unit's performance criteria to import into a moodle course as outcomes, ready to associate with each of your assignments. Here's a quick 'how to' for importing these into moodle 2.x
Registered Training Organisations
Trying to find someone to train or assess you? This link lists all the RTOs that are currently registered to deliver MEM18084, 'Commission and decommission split air conditioning systems'.
Google Links
links to google searches, with filtering in place to maximise the usefulness of the returned results
Books
Reference books for 'Commission and decommission split air conditioning systems' on fishpond.com.au. This online store has a huge range of books, pretty reasonable prices, free delivery in Australia *and* they give a small commission to ntisthis.com for every purchase, so go nuts :)


Elements and Performance Criteria

Elements describe the essential outcomes.

Performance criteria describe the performance needed to demonstrate achievement of the element.

1

Determine job requirements

1.1

Follow standard operating procedures (SOPs)

1.2

Comply with work health and safety (WHS) requirements at all times

1.3

Use appropriate personal protective equipment (PPE) in accordance with SOPs

1.4

Identify job requirements from specifications, drawings, job sheets or work instructions

2

Determine the operating conditions of vapour compression systems

2.1

Determine the actual and specified range of operating conditions from measured and calculated values using established procedures to determine as they apply to particular vapour compression systems

2.2

Establish operating conditions and record on commissioning documentation

2.3

Obtain tools, equipment and testing devices needed to determine the basic operating conditions and check for correct operation and safety

3

Recover refrigerants from split air conditioning systems

3.1

Check for, and protect site from, ignition sources if R32 or other flammable refrigerants are used

3.2

Isolate circuits/appliances in strict accordance with work health and safety (WHS) requirements and procedures, where necessary

3.3

Remove refrigerants safely into suitably labelled containers in accordance with legislative and industry requirements

3.4

Deal with contaminated refrigerant in accordance with requirements

4

Pressure and leak test split air conditioning systems

4.1

Identify and note safety hazards and implement established risk control measures

4.2

Follow industry codes of practice and manufacturer installation instructions

4.3

Take precautions to prevent damage to components while pressure testing the system

4.4

Conduct pressure testing at a pressure compatible with the refrigerant to be used

4.5

Located leak, isolate and repair using methods appropriate to the system type under test and in accordance with industry practices

5

Evacuate split air conditioning systems

5.1

Note safety hazards which have not previously been identified, and implement established risk control measures

5.2

Evacuate the system to the required level and clean the system of all moisture and other containments in accordance with requirements

5.3

Apply a standing vacuum test in accordance with industry codes of practice and applicable standards

6

Charge split air conditioning systems

6.1

Select correct refrigerant for the system, in accordance with manufacturer requirements and industry practices

6.2

Measure the refrigerant charge by weight in accordance with manufacturer specifications

6.3

Charge the system in accordance with manufacturer requirements and industry practices

6.4

Check all components and maintain in accordance with manufacturer requirements

7

Test the operation of split air conditioning systems

7.1

Start and operate the system

7.2

Carry out standard tests to confirm system performance to manufacturer specifications

7.3

Check the refrigerant charge and add refrigerant, if required

7.4

Leak check the system

7.5

Record test data, as required

8

Complete the commissioning/ recommissioning of split air conditioning systems

8.1

Ensure the worksite is cleaned and left in presentable condition in accordance with original presentation, client requirements, industry standards and organisational requirements

8.2

Undertake final inspections to ensure installation conforms to industry, legislative and work order requirements

8.3

Instruct the client on the use of the product in accordance with organisational requirements and manufacturer specifications

8.4

Complete certificates of compliance and other relevant commissioning documentation and process in accordance with state/territory regulatory requirements

9

Decommission split air conditioning systems

9.1

Electrically disconnect plug in appliance

9.2

Recover refrigerants, store and dispose of in accordance with legislative and industry requirements

9.3

Remove units and components and dispose of safely and in accordance with regulations, industry codes of practice and sustainable environmental practices

9.4

Clean the worksite and leave in presentable condition, to client and organisational requirements, industry standards and sustainable environmental practices

9.5

Complete decommissioning documentation and process in accordance with state/territory regulatory requirements


Qualifications and Skillsets

MEM18084 appears in the following qualifications:

  • MEM20105 - Certificate II in Engineering
  • MEM20105 - Certificate II in Engineering
  • MEM20105 - Certificate II in Engineering