Test and commission wind turbine control systems

Formats and tools

Unit Description
Reconstruct the unit from the xml and display it as an HTML page.
Assessment Tool
an assessor resource that builds a framework for writing an assessment tool
Assessment Template
generate a spreadsheet for marking this unit in a classroom environment. Put student names in the top row and check them off as they demonstrate competenece for each of the unit's elements and performance criteria.
Assessment Matrix
a slightly different format than the assessment template. A spreadsheet with unit names, elements and performance criteria in separate columns. Put assessment names in column headings to track which performance criteria each one covers. Good for ensuring that you've covered every one of the performance criteria with your assessment instrument (all assessement tools together).
Wiki Markup
mark up the unit in a wiki markup codes, ready to copy and paste into a wiki page. The output will work in most wikis but is designed to work particularly well as a Wikiversity learning project.
Evidence Guide
create an evidence guide for workplace assessment and RPL applicants
Competency Mapping Template
Unit of Competency Mapping – Information for Teachers/Assessors – Information for Learners. A template for developing assessments for a unit, which will help you to create valid, fair and reliable assessments for the unit, ready to give to trainers and students
Observation Checklist
create an observation checklist for workplace assessment and RPL applicants. This is similar to the evidence guide above, but a little shorter and friendlier on your printer. You will also need to create a seperate Assessor Marking Guide for guidelines on gathering evidence and a list of key points for each activity observed using the unit's range statement, required skills and evidence required (see the unit's html page for details)

Self Assessment Survey
A form for students to assess thier current skill levels against each of the unit's performance criteria. Cut and paste into a web document or print and distribute in hard copy.
Moodle Outcomes
Create a csv file of the unit's performance criteria to import into a moodle course as outcomes, ready to associate with each of your assignments. Here's a quick 'how to' for importing these into moodle 2.x
Registered Training Organisations
Trying to find someone to train or assess you? This link lists all the RTOs that are currently registered to deliver UEPMNT436, 'Test and commission wind turbine control systems'.
Google Links
links to google searches, with filtering in place to maximise the usefulness of the returned results
Books
Reference books for 'Test and commission wind turbine control systems' on fishpond.com.au. This online store has a huge range of books, pretty reasonable prices, free delivery in Australia *and* they give a small commission to ntisthis.com for every purchase, so go nuts :)


Elements and Performance Criteria

ELEMENTS

PERFORMANCE CRITERIA

Elements describe the essential outcomes.

Performance criteria describe the performance needed to demonstrate achievement of the element.

1

Plan and prepare for work

1.1

Requirements including scope of work and assigned roles are identified and confirmed with appropriate personnel or by site inspection, in accordance with workplace procedures

1.2

Work, Health and Safety (WHS)/Occupational Health and Safety (OHS) regulations, legislative requirements, industry standards, codes of practice, manufacturers’ specifications, environmental obligations and workplace procedures are reviewed in preparation for work

1.3

Resources are obtained and inspected for compliance with job specification

1.4

Relevant plans, drawings and manuals are selected and used, in accordance with workplace procedures

1.5

Correct materials and components for work are obtained and inspected for compliance with job specification

1.6

Plan for commissioning of wind turbine control system is developed, in accordance with workplace procedures, including sequencing and prioritising

1.7

Potential hazards are identified and risk control measures are implemented, in accordance with workplace procedures

1.8

Work area is prepared in accordance with workplace procedures

2

Test systems equipment

2.1

Isolations are confirmed, where appropriate, in accordance with workplace procedures

2.2

Wind turbine control system equipment is visually inspected to ensure absence of any damage, defects or deterioration, in accordance with workplace procedures and commissioning plan

2.3

Wind turbine control system equipment is tested, in conjunction with other related systems and equipment, to ensure correct operation, in accordance with workplace procedures and commissioning plan

2.4

Wind turbine control system wiring system is checked and tested, in conjunction with other related systems and equipment, in accordance with workplace procedures and commissioning plan

3

Test system

3.1

Isolations are confirmed, where appropriate, in accordance with workplace procedures

3.2

Wind turbine control system is visually inspected to ensure absence of any damage, defects or deterioration, in accordance with workplace procedures and commissioning plan

3.3

Wind turbine control system is tested using appropriate plans, drawings and manuals, in accordance with workplace procedures and commissioning plan

3.4

Wind turbine control system is tested, in conjunction with other related systems and equipment, in accordance with workplace procedures and commissioning plan

3.5

Wind turbine control system test results are interpreted and documented, in accordance with workplace procedures, to confirm compliance with commissioning plan

4

Commission system

4.1

Isolations are confirmed, where appropriate, in accordance with workplace procedures

4.2

Wind turbine control system plant and equipment is set up, in accordance with workplace procedures, to meet operational requirements and manufacturers' specifications

4.3

Wind turbine control system is set up, in accordance with workplace procedures, to meet operational requirements and manufacturers' specifications

4.4

Wind turbine control system plans, drawings and manuals are used, in accordance with workplace procedures and commissioning plan

4.5

Wind turbine control system equipment is commissioned, in accordance with workplace procedures and commissioning plan

4.6

Faulty wind turbine control system equipment is repaired, or reported, in accordance with workplace procedures

4.7

Final inspection is carried out, in accordance with workplace procedures

5

Complete work

5.1

Wind turbine control system commissioning is completed, and appropriate personnel are notified, in accordance with workplace procedures

5.2

Work area is cleared of waste, cleaned, restored and secured in accordance with workplace procedures

5.3

Tools and equipment are maintained and stored, in accordance with workplace procedures

5.4

Work completion details are finalised in accordance with workplace procedures